We noticed that the bill of materials requirements in a production order were incorrect. It requires more than the required amount. When we checked the main data, additional data and product tree of the material, we saw that the correct quantities were included, but the requirements in the work order do not appear correct. Is there another area I should check? Is there anyone who can help?