Block Technical completion.

atul_sharma3
Participant
0 Kudos
1,645

Hi guru's,

when we do permit  for WO then i did it before release after,i am saving my WO then internal error is occurred BLTC(Block Technical completion).when i completed my WO then i am doing to dp TECO then Black flag option is hide on top bar and also in order  option.
Regards
atul

Accepted Solutions (0)

Answers (8)

Answers (8)

hasan_ahmed1
Active Participant
0 Kudos

Hi,

Though it is old thread but still no one has answered and I was also stopped at the same step.

Resolution as below.

IW32- Ctrl+F8--> check the NR(Not Relevant) checkbox and WCM sys status will disappear and TECO icon will come.

Thanks

Hidayath

atul_sharma3
Participant
0 Kudos

hi guru's

this is the picture first

BLTC Block technical completi

WCM  Work Clearance Managemen

REL  Released

NMAT No material components

PRC  Pre-costed

atul_sharma3
Participant
0 Kudos

Hi vemuri sir,

i opened this and nthing is there like you said

peter_atkin
Active Contributor
0 Kudos

Atul,

Can you send a screen-shot of your order header - the same as the image posted above.

PeteA

atul_sharma3
Participant
0 Kudos

Hi,

i think that have some work in configuration in development side. plz tell me sir.

atul_sharma3
Participant
0 Kudos

will you plz tell me the whole process because i have not idea about it because our consultant did a by pass like they made one t-code and direct Approvals. but that approvals is not in sap just manually so plz tell me the whole WCM procedure. it can help our saftey dept. and also for audit.


Best regards,

Atul

atul_sharma3
Participant
0 Kudos

Hi Mane,

Mean yes in my system status--WCM  REL  NMAT PRC so i have to do work on WCM side mean safety module to clear it all then it will show to me. i am right

Atul

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Atul,

Yes - process your WCM objects (Work Approval, WCA, WCD if required).

Alternatively, in IW32 in the "Permits" window you can select the "ND" flag next to your Permit (but in Production system this should only happen where the process alows that and work clearance process does not apply!)

rakesh_mane
Active Contributor
0 Kudos

Hello

yes correct, work on WCM side

Br

Rakesh

rakesh_mane
Active Contributor
0 Kudos

Hello

WCM is active on Work Order.Please do the necessary action from WCM side then TECO flag will appear.

Br

Rakesh

atul_sharma3
Participant
0 Kudos

sorry i can't give my one point. so how can i do this and solve this BLTC

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Atul,


Sorry, this question is not entriely clear to me.

Have you assigned the Permit to the Order?

Is the Permit issued (green) on the Order?

Is the Permit defined as 2 - Mandatory for Completion in IPMD?

Former Member
0 Kudos

Hi,

Check in the service order for User statuses

check in OIBS transaction if any user status as Business transaction enabled for BLTC