Billing Element at WBS element level

1,683

Hi Team,

Public Cloud: Project defined with "Project with Revenue" profile. Now system is allowing Billing Element indicator at Project level only but not at WBS element level.

Because of the above reason, System is not allowing to maintain WBS element as account assignment at SO item level.

We need Billing element option for all WBS element level. Please provide the solution.

Regards,

Sairavi

View Entire Topic

Hi Gary,

We tried the same but system is not allowing to save project without billing element check box since project is defined as Project with Revenue.

Any other options, Please guide.

Regards,

Sairavi

Dharyl
Explorer
Were you able to find a solution for this?
huny
Explorer
0 Kudos
Were you able to find a solution for this?
Dharyl
Explorer
0 Kudos
You need to uncheck the box before releasing the project, that will allow to check the revenue box for the other WBS elements, do this in the project planning app