on 2007 Dec 03 11:23 AM
Hi experts
I created the process order and did the consumption and TECO for the order. Due to some reasons i revoked the TECO. Here i am facing the problem.
Initially some raw materials are not batch managed. Now in the mean time MM team has activated the batch management active for all raw materials.
When revoke the TECO now, the system asking the batch number for raw materials, the batch number column is not editable now. I am not able to do the revoke of TECO.
How to rectify it?
Thanks in advance
Do reverse posting for all ROH (262) then again re issue the ROH with newly craeted Batch.TECO only not allow user to change the Production Order.We can able to post the material even after TECO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you can deactivate the concern material from batch management
or else post some stock with batch number for that material and give the number
give me the reply how it works
sasikanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.