on 2025 Apr 21 7:38 AM
Hello,
I have a BOM and its components are batch managed. The finished item is also a batch managed.
How can I manage the batch's transactions in easy way and assign batch of component to batch of finished item?
I have SAP B1 10. In Administration -> System Initialization -> General settings -> Inventory -> Management Method is "On every transaction"
I hope I was clear enough and I was able to explain the issue.
Thank you in advance!
Request clarification before answering.
Hi @MarinaLevy ,
When on production order, you first need to issue the components. SAP will prompt the batch selection window.
Then, you receipt the final product. Here, you are creating the batch for the finished goods.
Finally, you can run a report to track the batches assigned to the Production Order
If you're not able to perform any of these steps, please provide details. I hope it helps.
BR,
Felipe
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @MarinaLevy ,
Your production order must be released and you have to right-click and select "Issue Components". Report completion follows same steps.