on ‎2022 May 03 1:45 PM
I tried many times to use BAPI_CUSTOMERQUOTATION_CHANGE for changing the quantity in Quotation and I am not able,
I have applied the U for updating instead of X, but nothing is reflected in the quotation.
I executed also with Commit but nothing work.
The quantity which I entered in the schedule line is always adding to the ordered quantity...How I can reduce the quantity or if it is possible to overwrite it ?!
Request clarification before answering.
Hi,
You need to fill in SCHEDULE_LINES & SCHEDULE_LINESX accordingly.