on 2009 Jan 29 8:45 AM
Hi Gurus,
System always confirms stock in sales order when availability check is with RLT since it assumes it will have stock at the end of RLT.
I want to know that what happens when availability check is done without RLT in sales order. Does it confirm stock in sales order? If its confirmed then how it will be confirmed
Thanks
Vimal
Dear Vimal,
If the stock is available system will confirm the availability. Otherwise, you need reconfirm the order once the stock is updated. You can do this using rescheduling or back order processing.
If you want the system to check the replenishment lead time, you should make sure that you have entered a value in at least one of the following three fields in the material master:
GR (goods receipt) processing time (Purchasing view)
Planned delivery time (MRP I view)
GR processing time (MRP II view)
Otherwise, the system confirms every requirement.
Hope this suffice,
Pl award marks if this is satisfactory or ask for more details!
Mukhraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
9 | |
8 | |
6 | |
5 | |
5 | |
4 | |
4 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.