on 2023 Sep 07 9:47 AM
I can see there is Overhead Value category is displaying in cost tab with Zero Value. I have only activity type available in Operation tab for which planned cost determined. I have checked the assignment of Overhead in value category to cost element and have different cost element that my activity type. Hi All expert Kindly tell me why it is displaying automatically.
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Correct. It is working now after removing Overhead from the suggested path "Define Default Values for Value Categories".
Thank you for the quick help.