Hi Team,

 

Even after enabling automatic GR at:

 

  1. control key assigned to routing
  2. work center
  3. Production scheduling profile and assigning it to material,

we are not able to post automatic goods receipt during production order confirmation. Please have a look at the attached example with the last screenshot showing production orders in 'confirmed status' where as they should have been in 'delivered' status after confirmation.

Is there anything else that needs to be done? 

View Entire Topic
Mateus_Blume
Product and Topic Expert
Product and Topic Expert
0 Kudos

For more details about goods movements during confirmation, please take a look at the following link from SAP help:

Best regards,