Hi to all, we are in a conversion project from ECC to S4.
In this case we have this scenario:
Material AAA. There is a valid Qty contract 46000001
NO Info record. No Source list created. No SourceList relevant in Purchasing view in material.
When running MD03 the program creates a PR but with this contract assinged. WHY??
as I said, there is no IR and no SourceList.
I was not able to find a response to this.
Any ideas?
Request clarification before answering.
Hi,
please check the following KBA, in which the source determination for MRP in S/4HANA is explained: 2614920 - Sourcing priority during MRP in S/4 HANA system.
If there's only a single purchasing contract available for a specific product, this will be determined during MRP run.
Best
Andreas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
17 | |
8 | |
7 | |
6 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.