Dear experts,

We need to have a background confirmation of the components (semi finished goods) that are used in the BOM of a material, when we confirm this material.

Phantom assembly for the components is not preferrable since we need to confirm production orders at a specific Work Center with their routings.

Is there a way to set up a background job that will confirm automatically the necessary quantities of the components, that are requested when we confirm the quantity of a material code?

Thank you in advance.

Kostas Voulgaridis

Accepted Solutions (1)

Accepted Solutions (1)

beyhan_meyrali
Active Contributor

Hi,

You can check the table "AFFW" and build a z program to confirm and schedule it as background job.

Depending on your production type you need to related bapi to confirm.

REM Confirmation: BAPI_REPMANCONF1_CREATE_MTS.

Discrete Confirmation : BAPI_PRODORDCONF_CREATE_TT

Hope that helps.

Answers (1)

Answers (1)

beyhan_meyrali
Active Contributor
0 Kudos

Hi gargantoua,

I think you need to enable COGI.

former_member772028
Participant
0 Kudos

thank you for your answer.

COGI is enabled. Is there a way to set a background Job (e.g. automatic confirmation) in Cogi?

We need this for specific materials.