Hi,

We are in a scenario, where we need Auto-UD and stock posting to happen on the inspection End date of the inspection lot. Basically, the stock needs to be available in Unrestricted after 5 days of GR (hence kept AID as 5). Pls advise.

Note: Configuration changes (Waiting time for Auto-UD) might work, but we have different number of days for different materials. So, if auto-UD is based on the Inspection end date, then will be perfect for the purpose.

Accepted Solutions (1)

Accepted Solutions (1)

former_member42743
Active Contributor

You'll have to copy the auto UD program and add additional logic to this. It shouldn't be difficult to add an If-then statement to check of the inspection lot end date = the current system date.

If you want to post the stock but not make the UD, you'll need a custom program to do that.