on 2018 Jul 24 4:14 PM
atp-check.jpgHi all,
I have a problem with ATP check. I have a component used in production order and also for external working (purchase order for subcontracting).We suppose that I have 20 pc for material A.
I run atp check in Purchase order for component A and ATP conferm me all quantity. Then i run ATP check in production order and the system conferm me all quantity. Can you help me?
I attach screen shot of atp check. M =purchase order; PP = Production order.
Best regards
Giuseppe C.
Request clarification before answering.