on 2016 Jun 21 10:32 AM
Dear Experiment ,
I need to know What happens if I don't maintain this configuration : SPRO ----->Enterprise Structure------>Plant Maintenance----->Assign maintenance planning plant to maintenance plant , And effect that in the maintenance process
i.e : i defined maintenance planning plant in the system
Thanks a lot
Asjad
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you don't maintain the configuration under **SPRO → Enterprise Structure → Plant Maintenance → Assign Maintenance Planning Plant to Maintenance Plant**, it can have the following effects on the maintenance process: ###
1. **Planning Plant and Maintenance Plant Relationship** - In SAP PM (Plant Maintenance), the **planning plant** is responsible for planning and coordinating maintenance activities, while the **maintenance plant** represents the physical location where maintenance activities are carried out. - If the assignment between the **maintenance plant** and **planning plant** is missing, the system will not recognize which plant should handle planning responsibilities for the maintenance plant. This leads to inconsistencies or errors in processing maintenance orders, notifications, and tasks. ###
2. **Impact on Master Data** - **Functional Locations** and **Equipment** are assigned to a maintenance plant. If there’s no link to a planning plant, these objects might not be properly considered in maintenance planning and scheduling processes. - For example, when creating maintenance notifications or orders, the system may not determine the correct planning plant, resulting in errors or requiring manual intervention. ###
3. **Effect on Maintenance Notifications and Orders** - Without this assignment: - When creating a **maintenance notification** or **work order**, the system may not know where to route planning activities, causing errors or failures during document creation. - Maintenance orders may not correctly determine cost centers or work centers, which could disrupt execution and cost settlement. ###
4. **Cross-Plant Planning Issues** - If your organization requires cross-plant maintenance (e.g., one plant plans maintenance activities for another plant), this assignment is critical. Without it, the planning responsibility for the maintenance plant cannot be assigned to another planning plant. ###
5. **Error Messages** - The system might display error messages such as: - "No maintenance planning plant assigned to maintenance plant." - "Planning data is missing for the maintenance plant." ### **Recommendations** -
**Always maintain this configuration** to ensure a clear relationship between maintenance and planning plants. -
If you have multiple maintenance plants sharing a single planning plant, explicitly configure those assignments. -
Perform proper testing after the configuration to ensure that maintenance notifications and orders are created without errors. By maintaining this assignment, you enable smooth coordination between planning and execution in the SAP PM module.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just take it in such a way that u cannot plan any maintenance activity without a planning plant , for that only you need to assign one maintenance plant as a planning plant .
Planning plant is somewhat like more superior than maintenance plant . Moreover maintenance plant is also much important like Planning plant .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for visiting SAP Community to get answers to your questions. Since you're asking a question here for the first time please note that:
You are adding a comment to an old post that is not likely to get an answer.
I suggest starting a new question and following these guidelines:
I recommend that you familiarize yourself with: https://community.sap.com/resources/questions-and-answers, as it provides tips for preparing questions that draw responses from our members.
For example, you can:
- outline what steps you took to find answers (and why they weren't helpful)
- share screenshots of what you've seen/done
- make sure you've applied the appropriate tags
- use a more descriptive subject line
The more details you provide, the more likely it is that members will be able to respond. Feel free to also take our Q&A tutorial at: https://developers.sap.com/tutorials/community-qa.html
Should you wish, you can revise your question by selecting Actions, then Edit.
By adding a picture to your profile you encourage readers to respond: https://developers.sap.com/tutorials/community-profile.html
Regards,
Dedi
Hi Asjad,
A plant is responsible for planning maintenance activities. In this context, the plant is called as a planning plant. To convert a plant to a planning plant SPRO ----->Enterprise Structure------>Definition------>Plant Maintenance-----> Maintain Maintenance planning plant.
All the technical objects to be maintained are physically present in a plant. Here, the plant is known as a maintenance plant. A plant becomes a maintenance plant if you create a technical object there.
To define the planning plant responsible for the maintenance plant you assign maintenance planning plant to maintenance plant.
The above information is from plant maintenance perspective.
With Regards,
PS R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
According to organisational structure.
Assignment of maintenance planning plant to maintenance plant is important ,because it is a bridge between the other modules and PM stuff
moreover ,
Without assigning you cannot plan your work for functional location and equipment
you cannot plan work order
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Asjad,
First thing a PM consultant do this...
this is the bridge between PM and other modules like MM,SD< FICO... etc
If your not assigned MPP to MP,
You cannot plan your work for the technical objects like Functional Location,Equipment which is installed in the Maintenance Plant.
You cannot schedule your Work Orders.
You cannot plan for the Materials.
So,You must assign MPP to MP. Because its integrate with Other modules.
BR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 28 | |
| 14 | |
| 13 | |
| 6 | |
| 5 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.