on ‎2009 Dec 17 8:54 AM
Hi,
We use calendar year fiscal year variant.
fiscal year 2009 closed on 30.09.2009.
In 2010 when try to do asset disposal , error comes like
SYST: You cannot determine the period for rule 02 to 17.12.09
Message no. AA 613
Diagnosis
The system could not determine depreciation periods on 17.12.09 for
period control 02 of calculation key 0000.
Procedure
Maintain the allocation of the periods for the period control you
entered.
Proceed
If the period control you entered is a standard period control, you can
set up the allocation of periods automatically.
how to do teh disposal..?
thanks
neha
Request clarification before answering.
issue solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Steps:
1) Do the Define Calendar Assignments ( Under Valution Methods -> Period Control) for the Respective FY Variant and Month and Period or Maintain that respective should have all the values for Period control.
2) Then Generate the Period Controls in test mode first and then Real mode.
It should fix the above issue.
Thanks
Meenakshi.N
Hi
As said above AFAMP is a standard TCode.
Check this path
IMG -->Financial Accounting -->Asset Accounting -->Depreciation -->Valuation Methods -->Depreciation Key -->Calculation Methods -->Maintain Period Control Methods.
BUT you said your's is Calendar Year Fiscal Year variant, means your's is January - December. RIGHT.
And you mentioned fiscal year 2009 closed on 30.09.2009.
If you have Opened 2010 Fiscal year, then it should also be Jan - Dec. RIGHT.
Then what about these Oct, Nov & Dec Periods?
In which period you are trying to do Asset Scrapping using ABAVN.
Kindly let me know
Regards
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks
Ours is SAP old version . hence AFAMP is not there nor the navigation you mentioned.
T code OA84 has setup period control rules.
i also see OAVH with main of period control.
we have few co codes. One has fiscal year defined with Z1 variant august to sep. othersis K1 - jan to dec.
for co which has z1, when we do disposal in dec 09 it is giving above error. For this co we are already in fiscal yaer 2010.
I don't find an entry in OAVH for Z1.
But K1 it do exist. what should I do to generate an entry here..?
i believe period rule has to be defined once for calendar year variant during implementation not an yearly activity.
If it is year dependant variant, do we have to generate period control yearly..?
In OB29, I can see that properties, don't have neither calendar Year nor Year-dependant enabled.
is error related to thsi. coz in
rgds,
neha
Dear,
Check your period control setting in AFAMP, take the acquisition as 06.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 34 | |
| 18 | |
| 15 | |
| 14 | |
| 9 | |
| 4 | |
| 3 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.