After blocking some dates, still i am able to see the delivery in Md04

MudiamReddy
Participant
0 Kudos
314

Hi Team,

As per the business process we blocked some dates in the planning calendar  and we are

using the lot size key with the schedule key as "2", means delivery at the end of the period.

Now some blocked dates are falling at the period end and as per the lot size key we expected

delivery at the end of the period.Hence please let me know what is the hierarchy among the

lot size key and the planning calendar.

Best Regards

Bhagee

View Entire Topic
UmeshMali4994
Active Contributor
0 Kudos

Hello Eswar,

If possible share the Screen shot of the planning calendar Period and MD04 screen shot for more understanding.

1. Planning calendar calculate the date base on calculation rule defined in planning calendar.

2. Planning calendar depend on the factory calendar working day

3. Cross check the Material master input filed, which Planning calendar and Lot size assigned

4. share the lot size screen shot

Please refer below document for your reference

I hope this information helpful to you

Regards

Umesh Mali

MudiamReddy
Participant
0 Kudos

Hi Umesh,

Please find the relevant screen shots with respect to the issue.In the Md04 screen we are able to see the schedule lines on 06/01/2016. But this dates are blocked in the planning calendar ZXX.

And the used lot size key details as follows

BR

Bhagee

UmeshMali4994
Active Contributor
0 Kudos

Hello Eswar,

As per your Planning calendar Period list and Lot size It is behave correctly.

In you planning calendar you have period of 05/26/2016 to 01/06/2016 and as per lot size it will deliver on period end date, Md04 screen show as 01/06/2016. which is correct for this period.

Please share your calculation rules details of planning calendar and how you block the date in planning calendar ?

As per my understanding, Your changes are not reflected  in Planning calendar because your existing planning calendar period has firmed indicator (*)

Please remove the firming indicator once and re calculate the Planning calendar and check the result.

Please check and revert

Umesh Mali

MudiamReddy
Participant
0 Kudos

Hi Umesh,

Thanks for clarification.Please find the calculation rule for the planning calendar.

BR

Bhagee

MudiamReddy
Participant
0 Kudos

Hi Umesh,

I forgot to add the screen shot in that reply.please find the below screen shot.

BR

Bhagee

UmeshMali4994
Active Contributor
0 Kudos

As per calculation rule every monday requirement will created,
In the case of non working day system will consider the previous working day and create the order.

As you had couple of period set with firmed indicator, so remove all the firmed indicator first then save the planning calendar and again go to change mode and recalculate the factory calendar rules and check the period. Make sure all your blocking date should not populated in planning calendar period 

How you block the planning calendar date?

Please check the above step and revert

Please check the planning calendar document in details for your requirement

Regards
Umesh Mali

MudiamReddy
Participant
0 Kudos

Hi Umesh,

I too don't have clear idea how to block the dates in the Planning calendar.

If o you have any clear idea on this please share the required information and

i will make the necessary changes as per your comment in the previous thread

and i will revert.

Thanks

Bhagee

UmeshMali4994
Active Contributor
0 Kudos

Hello Eswar,

Planning calendar Date depend on the Factory calendar dates, and if factory calendar has non working day and same day period start date fall in that case Planning calendar consider the period date as per planning calendar calculation rule selection. 

Ex. 1. do not displace, 2. Previous working day 3. Previous working day 4. No new period.

Please check the document for detail functionality of calculation rule.

There is no additional rule available to block the date in planning calendar. You can select the planning calendar rule as per your requirement and calculate the period.

In your planning calendar case, you have set as every Monday calculation rule and delivery date set as Period end date.

Please remove the all period firmed indicator in your planning calendar (Yellow marked) and save the changes

Again go to change mode and with proper selection of the date and execute the period calculation.

It will show all the correct period.

Please follow the above step and share the details.

Regards

Umesh Mali

MudiamReddy
Participant
0 Kudos

Hi Umesh,

Thanks for clear explanation. i will revert you after completion of the above said things.

BR

Bhagee