on 2024 Jul 31 1:30 PM
Hi everyone!
I have a scenario in SAP AFS that I need the requirement type SB "DepReq planned order" could reduce the PIR in the MRP.
Scenario; I have a material A that is planned and we input the PIR for it and I have a Material B that is not planned but the material A is inside the BOM of the material B so I need to reduce the PIR of the material A (TAB 3 of the MRP) when there is a sales order for the material B, is it possible?
I could not find the path to configure the AFS Requirments Type.
Request clarification before answering.