on 2023 Nov 03 10:44 AM
Hi all,
I have an issue with my Advanced Scheduling Board in Fiori. I have set up the alternative resource correctly (classes and characteristics). It works on the Detailed Scheduling Board in GUI and it also works on the older Fiori app "Production Scheduling Board". I am also able to see under "Operation Information" that the Alternative Resource is acknowledged by the Fiori App.
And if i jump directly into the Order Processing from the Scheduling Board I can also see the Alternatives in here.
However, if I try to Drag & Drop the operation to the alternative resource it returns "Rescheduling executed succesfully" without changing the Resource.
I have tried with all combination of Strategy as well (current mode: Retain and Select Any Mode).
Please let me know if you have an idea or the solution for make it work!
Request clarification before answering.
Dear Thomas,
Unfortunately, it seems to be taking longer than usual for your question to be answered. You might want to try an alternative route to speed things up.
Please check if a similar question has already been asked in the Community. We have found that sometimes questions that have been answered before are no longer receiving responses.
The easiest way to do this, is to visit the All Questions page and search for your specific topic.
You could also check the SAP Support Portal and search for SAP Notes, SAP Knowledge Base Articles and more.
If all of this doesn’t work, I would suggest that you create a support ticket. All you need to do is log onto the SAP Support Portal with your S-user ID and password: http://service.sap.com/message
Thank you,
Necla
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
9 | |
7 | |
6 | |
4 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.