Hello,
Can someone advice what is the total number of days and resources required required to design, configure and unit test , quality test the following two items . If someone pls can give answer based on certain assumptions that will be also fine.
1) Advanced inter company sales
2) Advanced customer returns.
rgds
sar
Request clarification before answering.
Hi
The total number of days and resources required for Advanced Intercompany Sales and Advanced Customer Returns in SAP depends on various factors like complexity, system landscape, integrations, and business requirements.
Estimated Duration: 30–40 Days
Design & Blueprinting: 5–7 Days
Configuration & Unit Testing: 12–15 Days
Quality Testing (SIT, UAT): 8–10 Days
Fixing & Refinement: 5–7 Days
Resources Required:
1 SAP SD Consultant
1 SAP MM Consultant (if procurement is involved)
1 SAP FI Consultant (for intercompany billing)
1 Tester (for UAT)
Assumptions:
Standard intercompany setup with automated billing and logistics
Minimal custom development
Integration with Finance and MM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 22 | |
| 15 | |
| 14 | |
| 5 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.