on 2023 May 24 6:36 AM
While booking timesheet actual cost not reflecting in Plan cost report - Plan/Actual.
Followed steps.
1. We have maintained Employee details in manage workforce app (Service cost level) cost center and company code,
2. Sales price, manage plan cost rate, manage Actual cost rate.
3. Created a project and assigned resource to the work package
Request clarification before answering.
Please check if Period is not open in manage posting period - cost accounting app for the fiscal year and company code.
When this period was opened, actuals (timesheet posting) got reflected in the report.