Account Assignment P - Goods receipt for Project Orders with material code for stock

amara164
Discoverer
0 Kudos
122

 We are trying to do a Goods Receipt of Account Assignment P – Purchase Order WITH MATERIAL CODE and we could see that the material is getting consumed on the WBS but is not generating inventory for processing.

 Business wants  to use Project PO for stock .  Can you please advise how we can implement the requirement.

Accepted Solutions (0)

Answers (1)

Answers (1)

Mandardesh01
Explorer
0 Kudos

Hi Amara

what you need is account assignment Q where project specific inventory gets generated rather than direct consumption on WBS like  Account assignment category P .

SAP does not support the functionality in Public cloud for Project stock for projects with Revenue, 

following  blog mentions the same,

https://community.sap.com/t5/enterprise-resource-planning-blog-posts-by-sap/how-to-leverage-project-...

Other useful references for you 

https://me.sap.com/notes/3590678/E

https://community.sap.com/t5/enterprise-resource-planning-blog-posts-by-sap/enterprise-portfolio-and....

Regards