Hi expert.
When posting confirmation for production order, there is an issue where the Standard Price used is the Standard Price from last month.
If there is a sudden need for production during the month, or depending on the timing of evaluation, last month's Standard Price may be used.
One way to avoid this is to perform a Costing Run at the end of the previous month, but this can be difficult in some cases.
At this time, is there a way to output a message when trying to evaluate using last month's Standard Price?
If possible, I would like to achieve this using only Standard Functions.
(Ver ECC6.0 EHP4)
Thank you
Request clarification before answering.
You can use CMOD to do the enhancement.
Pls use "CONFPP02" when do the confirmation enhancement, exit is EXIT_SAPLCORF_102 to check if the product material has standard price.
Or you can use PPCO0001 when saved production order enhancement, exit is EXIT_SAPLCOBT_001 to check if the product material has standard price.
BTW, most of project will check whether the cost estimate released for the materials when saved the production order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 28 | |
| 14 | |
| 13 | |
| 6 | |
| 5 | |
| 5 | |
| 4 | |
| 4 | |
| 4 | |
| 4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.