Hi Experts,
Please help me understand if the below scenario is doable under Standard ABC Product Substitution scope:
1. We have 3 products A, B, and C which need to be replaced by D when a customer places the order in the following way: A= 10, B= 15, C=20 in a single order, and all should be replaced by D with 45 (A+B+C).
2. There are 2 parts in the above scenario: I) A, B and C need to be replaced with D and II) Qty adjustments as per the given example. Any of these are achievable in Standard ABC, please guide.
Thanks in advance.
Regards,
Arindam
Request clarification before answering.
Hello Arindam,
As per my understanding,
1) In your first question, should only one subitem be created as all 3 products are substituted by D and the sufficient stock is available.
Eg : A->D, B->D, and C->D in product substitution belonging to same plant.
But assume that only 35 quantity of D is available, then which product should give remaining 15 quantity?
Regards,
Naveen Kumar Chikkanna.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
119 | |
8 | |
7 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.