on 2013 Jan 09 11:22 AM
Hi Experts,
How to configure only 1,3 Saturdays as day off. Through PWS.... 5 th Saturday is also generating as Day Off which is wrong. IT should be paid/work.Do we have any other solution other than User Exit.
Regards,
Chris
Below is sample for 2nd and 4th saturday off.......OR I will suggest use USER Exit - create a single PWS with day (ex:sat ) as off, and implement the exit PTIM2007.
1)Please notify the 2nd and 4th Saturdays for each month in that financial/Calendar year
2)You may use the following Navigation Path: IMG->SPRO->Time Management-> Work Schedule->Day Types->Define Special Days
OR Table "T553S"
3)Configure a Rule with the Day Type “03”
4)Configure Selection Rule and assign it to the Work Schedule Rule
5) Generate Work Schedules
Sushilkumar.M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
8 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.