Preventive maintenance plans are created to ensure that various assets are maintained based on maintenance strategies and program. A meticulous planner may create large number of plans that generates work orders autonomously.

As organization become mature and they move from break fix mode to proactive mode of managing assets, planner needs to evolve maintenance strategies to more optimized inspection, preventive /corrective activities making some of the existing maintenance plans irrelevant in future. There are multiple use cases where planner needs to ensure that system does not propose new preventive activities for plans that would not be relevant in future, e.g. End of warranty related checks, planned improvement / modification project resulting in change of maintenance strategies etc.

Now with SAP EAM, you can effectively stop a preventive maintenance plan based on a date in future or counter value the asset may reach in future.



Fig:1 Time based, counter based plans with end date for scheduling and end counter for scheduling

 

Once the date or counter value is set, during scheduling run, system ensure that it does not create calls only for the events that is next to end date or end counter.

To get the visibility on how many days are left for a maintenance plans, IP15 and IP16 are enhanced to show remaining number of days or remaining number of counts.



Fig 2: Enhanced IP15 with additional information about remaining  days or counters

This enhancement along with enhancements described below would help a maintenance planner to implement proactive management of preventive activities

To enable this feature, you may need to implement Note # 2712672. This note is valid from EhP7 and all the release of SAP S/4HANA. You will need First implement note 2721764 - (LOG_EAM_CI_13) if the Business Function does not exist yet in your system.

You will get further information about this new feature from help document link.

You will find more information in SAP Improvement Finder

Mark master blog as favorite to get information about further improvements that would be released.
11 Comments
nirmalkokkuvayi
Participant
0 Kudos
Good option. Hope this will be standard feature in Ehp8.

 
hemantjivraj_rathod
Product and Topic Expert
Product and Topic Expert
Hello Nirmal,

thanks for pointing out my grammar mistake. This improvement note is available from Ehp7 and all releases after that including Ehp8, S/4 HANA 1511,  1610, 1709 and 1809. In future releases it is part of standard feature.

regards

Hemant
prashantmeshram
Explorer
0 Kudos
 

Hello Sir,

We are in S4 HANA 1809 103  and We have activated business function LOG_EAM_CI_13 But I am

not getting End scheduling field in the maintenance plan.

Please guide.
hemantjivraj_rathod
Product and Topic Expert
Product and Topic Expert
0 Kudos
Hope you were able to implement note properly and enable the fields as per the note/documentation.
prashantmeshram
Explorer
0 Kudos
Hello Sir,

After proper note implementation mention functionality working fine.

 

Thanks

Prashant Meshram
nirmalkokkuvayi
Participant
0 Kudos
Thank you Sir!
former_member198942
Contributor
0 Kudos
Mark master blog as favorite to get information about further improvements that would be released

 

How to mark this as favorite. Not getting an option.
YBS
Participant
0 Kudos
Hi,

Thank you for this document,

Please is this also available for maintenance plan with strategy without counter,

Thank you,

Regards,
YBS
Participant
0 Kudos
Hi Mister,

Thank you for your valuable content.

I have a question regarding the duration of the maintenance plan. In our case, we would like to generate notifications continuously until the end of the contract. However, I'm wondering why the duration field is still mandatory. Could the duration be calculated from the end of the contract? Alternatively, can I set it to a default value like 99 years, considering that the scheduling will always goes at the end of the contract?

Thank you,

Regards,
Adventurer
Participant
0 Kudos

Dear @hemantjivraj_rathod,

Is it available in S4H public cloud as well? I don't think so. If not, please remove the tag of S4HPC.

BR,

Amin

hemantjivraj_rathod
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Amin_S,

This features is available also in public cloud 🙂 Please check Manage Maintenance Plan app.

hemantjivraj_rathod_0-1735820214330.png

hemantjivraj_rathod_1-1735820247317.png

Hope this helps.

Best regards

Hemant