In this blog you will learn about the end-to-end service process from service quote to financial reporting for Service with Advanced Execution and Resource-related Billing. This service process flow is based on SAP S/4HANA Cloud Private Edition, release 2023. 

Picture1.png

 

For an introduction into Service with Advanced Execution, please check this blog: Introduction to Service with Advanced Execution 

 

Step 1: Service Quote

Create a Service Quote and enter one or multiple Execution Order items. The Execution Order item is used in the Service with Advanced Execution process and contains all commercial data for the service, like billing relevance and service contract assignment.

GertTackaert_0-1712044687062.png

For more information about Execution Order item, please check this blog: Execution Order item 

Step 2: Send the Quote to Customer and Accept the quote

The quote can be sent for approval to the customer. The status of the quote and quote items changes to Released. 

GertTackaert_1-1712044748992.png

 

After customer feedback, the quote can be Accepted or Rejected. When the quote is accepted, the status will change to Completed and a follow-up service order will automatically be created. All accepted execution order items are copied into the service order. 

GertTackaert_2-1712044818293.png

The follow-up service order can be found in the Transaction History of the service quote. 

 

Step 3: Review and Release Service Order

In the Service with Advanced Execution process, the service order is used to manage all commercial data. You can check the billing relevance and DIP profile in the details of the Execution Order item. This information is copied from quote into service order, and can still be adjusted in the service order. For Resource-related billing the billing relevance is "Itemized Billing" or "Summarized Billing", and a DIP profile is required.

GertTackaert_3-1712044929192.png

More information about Billing Relevance can be found in this blog: Billing Relevance 

DIP profiles can be managed using SAPGUI transaction ODP1.

GertTackaert_1-1712322948799.png

 

Detailed planning and execution is done in a connected maintenance order. To start the scheduling and execution process, the service order needs to be released and a maintenance order will be created. Details of the Maintenance Order are visible in the Execution Order Item details page and in the Transaction History. 

GertTackaert_4-1712045032519.png

 

Step 4: Plan and Release Maintenance Order

The maintenance order that gets created is an extended version of the standard maintenance order. The so-called "billable maintenance order" shows commercial data (like customer and service product), and it supports advance shipment of spare parts and customer-owned parts in the component list.

GertTackaert_0-1712321418525.png

 

A task list can be determined based on the service product or equipment. After planning, the maintenance order can be Released to start service execution.

GertTackaert_1-1712321494249.png

Releasing the Maintenance Order updates the Execution Status in the Service Order to 'In Execution'.

GertTackaert_2-1712321594844.png

 

Step 5: Create Maintenance Confirmation(s)

Using the Enter PM Order Confirmation (IW41) app, you can create confirmations for the planned operations and components. 

GertTackaert_3-1712321658991.png

 

Step 6: Finalize the work 

To finalize the service work, you can set the maintenance order status to Technically Complete. This status change in the maintenance order will automatically set the connected service order item to Completed and the Execution Status to 'Execution Done'. 

GertTackaert_4-1712321866807.png

 

GertTackaert_0-1712322639643.png

 

Step 7: Review cost postings

In the Display Line Items - Margin Analysis app, you can review the different cost postings. The costs have been booked on the maintenance order as Accounting Object and are attributed to the Service Order item. You also see that the cost postings have resulted in matching revenue recognition and WIP postings, depending on the revenue recognition method.

 

GertTackaert_5-1712321991405.png

 

Step 8: Resource-related Billing

Using the Create Resource-Related Billing Request - Service Order app, you can now start the creation of a Debit Memo Request based on the cost postings. Resource-related billing uses a Dynamic Item Processor (DIP) profile that is entered in the service quote or service order. This DIP profile defines how the service costs (labor and parts) are converted into billable items in the customer invoice. Resource-related billing can be either itemized billing or summarized billing. This is defined by the billing relevance in the execution order item.

GertTackaert_6-1712322097719.png

GertTackaert_0-1712558162137.png

The result is a Debit Memo Request

GertTackaert_0-1712560780466.png

 

Step 9: Create and post billing document

Using the Create Billing Documents app, the Debit Memo Request (DMR) can be turned into a Billing Document. 

GertTackaert_1-1712560957329.png

GertTackaert_2-1712561099086.png

The Debit Memo Request and Billing Document are included in the Transaction History of the Service Order. 

GertTackaert_3-1712561186286.png

 

Step 10: Review revenue postings

In the Display Line Items - Margin Analysis app, you can review the resulting revenue postings. You see that the revenue postings have also resulted in matching revenue recognition and WIP postings.

GertTackaert_4-1712561288781.png

This concludes this end-to-end service process

 

 