For Sales Orders, it is possible to maintain delivery dates for days that are specified as non-working days, like weekends or holidays. This is possible when the user enters a Requested Delivery Date (or a Delivery Date on the schedule line) for a day that falls on a non-working date according to the factory calendar of the unloading point. When this situation happens, the user receives a warning message (V1019) informing the user that the date selected falls on a non-working day.
The Customer's factory calendar is configured against the 'Customer: Unloading Point' in the customer master (app Maintain Business Partner).
In the example below the user will select a Public holiday as the 'Requested Delivery Date'. The date selected, according to the calendar of his unloading point, is a non-working date. In this case, the user will receive the following warning message:
System will not automatically force the next date because it keeps open the possibility that the customer will accept the delivery on a non-working day. It is possible that the goods are important for the customer and so the customer is disposed to accept a delivery on a non-working day. This is the standard behavior.
When the user presses enter, they by-pass this warning message informing the system that they accept the goods to be delivered on the non-working date.
In summary, the user has two options: