Repetitive Manufacturing(REM)

Company manufactures product in large numbers and production is quantity   based and period based not order based.

  • Repetitive manufacturing is mainly used for the production scenarios with high product stability, high repetition rates, and low product complexity.
  • In master data production versions and cost collector is must where this is not mandatory in discrete manufacturing.


Application Areas:

Industry Type: Mechanical engineering, Consumer goods, electronics, and many more

  • Tact-based Flow manufacturing
  • Period based production
  • Mass production

Difference b/w Discrete and REM

                          

REM Prerequisite

  1. REM Profile
  2. REM Indicator
  3. Production Version
  4. Product Cost Collector


SAP REM Full Cycle scenario


Basic Data:

  • Plant : TAJA
  • Company Code : 1000
  • Storage Loc : TA01
  • Material created :

Sir No

Material

Material Type

1

AIRCOIL

FERT

2

CORE

ROH

3

SLEEVE

ROH

Repetitive manufacturing profile to control how you want to carry out planning and back flushing in repetitive manufacturing

Basic control parameter of the REM Profile

  1.   Whether you want to backflush activities.
  2.   Whether you want to work with reporting points in make-to-stock REM
  3.   How you want to process errors which occur when back flushing

      Create the REM Profile:

SPRO Production Rep manufacturing Control Data  Create REM Profile Assistant (T-Codes: OPP3/OSP2)

With help of the REM profile assistant create the Make-to-Stock REM Profile “TJ” (REM Profile for plant TAJA) here GI backflush at GR posting check mark and RP backflush is mandatory/Optional(as per requirements)

                                

  • Here Planned order reduction period is given 3 , so In this period system reduces all planned orders and run schedule quantities in the period

           reduction


                                                  

  • Here below mention all movement type set for the REM profile TJ

                                                          


  • Create the finished material Air coil with Repetitive mfg. indicator and REM profile TJ maintained in material master see view MRP -4 , ( MM01)



                                                  

  • Please create and maintained the BOM(CS01) and routing/Rate routing (CA01/CA21)
  • Rate routing for top material Air Coil and assigned control key to the operation see in below pic, (T-codes: CA21), here control key using for UK01 and UK02 for operation. (Standard  SAP control key with milestone confirmation is PP01)


                            

  • Create the Control key UK 02, with ‘milestone confirmation’ with help of the T-codes OP67. 
  • The milestone confirmation is a special form of confirmation, in which the confirmation of one operation causes other operations or suboperations to be automatically confirmed at the same time.

                                          

  • Create the Production version T777 for finished material(Air coil) with help of material master change (MM02),  and in Selection method put indicator 2 or 3.

                                                          

  • Production version is combination of the BOM and Routing/Rate Routing. Overview of the production version T777, more than one production version created as per requirement and make sure current prod. Version not locked.


                                                  

                                           


  • As per REM profile selection for the product cost accounting

       

       There are two different type of cost accounting exit.

  1. Standard cost estimate per material.

You can create this cost estimate once in a period with reference to a routing. You can post activities on the basis of this cost estimate if you produce a material using only one production version in one period.

Using T-code: CK11N do the standard cost estimate for current date and period, And release this standard cost estimate through T-code: CK24.

  1. Preliminary costing for the product cost collector.

You can create this cost estimate per production version. This makes sense if you produce one material using different production versions and routing in one period.

Using T-code:KKF6N for create Preliminary cost estimation in REM.


  • Here we selected preliminary costing for the product cost collector in REM profile


                                              

  • Create the Plnd.Ind.Reqmnt(PIR) for the finished material Air coil with help of the T-code: MD61


                                                                                 

  • See the below pic of the stock requirement list after generating the demand without run MRP. (T-codes : MD04 )

                                 

  • After run the MRP with help of the MD02 for finished material(Air Coil), MRP element is RS and order type is PE 

                                             

  • In REM, we can do backflush(REM Confirmation) through  planned order or finished material using MFBF, here we selected the planned order


                                                              

  • Checking with Post with correction in tool bar of REM confirmation page before saving and get the detail information of the all transaction variant with all detail.


                                                            

  • After saving system posted GR and GI document(As per REM profile setting GR and GI done at same time)

                                                                                     

  • After the confirmation of the both planned order, good receipt done automatically and available stock is 20. MD04 Screen


                                                         

  • With help of the Document overview on MFBF tab, we know the detail of the GR and GI transaction, and with help of the Reverse tab we can reverse the process of movement and material back to the stock.


                                                              

I prepared this document for the understand the basic step of the SAP REM process, and i hope this document helpful to clear the basic concept of the  REM process.

Request to expert please correct me if any thing missing or wrong in this document.



                                                     

                                                                                                                                                                                      Umesh Mali

                                                                                                                                      SAP PP-QM Consultant

52 Comments
Former Member
0 Kudos

Hi Umesh,

Good document.

Can you please add about MF50 Planning table transaction detail into it.....

Regards

Piyush

UmeshMali4994
Active Contributor
0 Kudos

Hello Piyush,

Thanks, I will add the MF50 detail in this document.

Thanks & Regards

Umesh Mali

former_member222080
Participant
0 Kudos

Heelo Umesh

Good Understanding DOcument.Could you please Update Backflush Type,COGI processs

Suresh

former_member185379
Active Participant
0 Kudos

Hello Umesh, Document is very helpful..! Thanks

UmeshMali4994
Active Contributor
0 Kudos

Thanks Prashant ,,,,

maheshkumar_komatineni
Active Participant
0 Kudos

Hi Umesh,

thank you for sharing this valueble document. i tried it in my ides up to mfbf evererything fine there i am fetting error. No gr with backflush in case of reporting point logic w auto gr option.

can youy please tell what i have to do to coplete mfbf.

Thanks&regards,

Venkat.

UmeshMali4994
Active Contributor
0 Kudos

Hello Venkat,

Thanks for go through this document,


Please check the which control key assign in routing/rate routing, Milestone confirmation maintained for the this control key. Please make sure the
RP backflush checked on MFBF screen ( Because in REM profile we maintained the RP backflush Mandatory) and assign Operation number(Control key with milestone confirmation assigned)on the the Reporting point field on MFBF screen,

If you want to run this process without reporting point then simply make change in REM profile, select the RM backflush optional.

Revert back if facing any other issue,,

Regards

Umesh Mali

maheshkumar_komatineni
Active Participant
0 Kudos

Thank you umesh, gr posted.

Thanks&Regards,

Venkat.

maheshkumar_komatineni
Active Participant
0 Kudos

Hi Umesh,

what is the difference between doing direct MFBF and doing MFBF after MF50.

Thanks&Regards,

Venkat.

0 Kudos

Hi Umesh,

Very clear concepts define by you.

Thanks for your efforts.

Shailendra

UmeshMali4994
Active Contributor
0 Kudos

Thank you Shailedra,,

Regards

Umesh Mali

Former Member
0 Kudos

Hi Umesh,

Add about MF50 planning table to make this doc perfect & complete.

Waiting.....

Thanks

Piyush

Former Member
0 Kudos

Thanks for sharing. Very informative material. Keep it Up.

Regards'

Muhammad Saleem

Former Member
0 Kudos

Hi Umesh,

Clear interpretation of Repetitive Manufacturing.

Nice Effort!

Regards,

waqas

Former Member
0 Kudos

Hi,

It very coveragable documents,nice work,

Devendra

UmeshMali4994
Active Contributor
0 Kudos

Hello Piyush,

I will preparing planning table document and update very soon,,
Before end of this week,

Regards

Umesh Mali

UmeshMali4994
Active Contributor
0 Kudos

Hello,

Saleem, Ahmed, and Davendra thanks for compliment,,

Regards

Umesh Mali

former_member184595
Active Participant
0 Kudos

Hi Umesh,

Yes, the blog is useful. Appreciate if you can mention clearly about significance of MF50 - Planning Table. Is MF50 Mandatory or Optional etc.

Thanks for ur efforts. :smile:

UmeshMali4994
Active Contributor
0 Kudos

Hello Aditya ,,

Thanks for go through this document ,


MF50 is opetional in REM. I will prepare the document for MF50 and posting very soon  (It's delay due to offc work load :razz: )

Regards

Umesh Mali

Former Member
0 Kudos

hi umesh

Thanks for this doc. It was helpful. Can you also highlight how settlement / variance is done in case of REM with screen shots / T-codes. This will be helpful to me.

Regards

Sree

former_member208199
Active Participant
0 Kudos

Hi Umesh,

Document is simple, clear, understandable and intresting & covered entire cycle. Really useful.Super.

Can you also cover the MF50, MTO Scenorio, example on Normal backflusing and Report point back flushing, Activities posting during backflusing, how to collect and clear the errors in goods movement, liitle bit costing side(example on Preliminary costing and standard costing, Variance calculation, settlement) also please mention the Important T codes for reports (information).

Thanks for providing useful document. keep it up.

Former Member
0 Kudos

Hi Umesh,


Thanks a Lot for this doc.

It is very good & helpful.

UmeshMali4994
Active Contributor
0 Kudos

Hello all,,

Thanks sreekantha, Raj and SAP PPQM for valuable compliment,,,

Regards

Umesh Mali

chen_lei
Explorer
0 Kudos

Hi Umesh,

good documentation, very useful to understand the basic process of REM.

thanks a lot for sharing.

Former Member
0 Kudos

Thanks Umesh............

for sharing documentation

UmeshMali4994
Active Contributor
0 Kudos

Thanks  Chen and Pranav,,,

former_member194876
Participant
0 Kudos

Hi Umesh,

Please create new document that explains REM Profile details.

Former Member
0 Kudos

Hi Umesh,

A really good document! keep up the good job.

UmeshMali4994
Active Contributor
0 Kudos

Hello Avinash,

Surely, I will create REM Profile Document

If you have any issue regarding REM profile, you can directly post here also

Regards

Umesh Mali

UmeshMali4994
Active Contributor
0 Kudos

Hello CB

Thanks for Compliment...!!! :smile:

Regards

Umesh Mali

Former Member
0 Kudos

hi umesh,

very very good  document! thank you very much sharing this very useful to me.

Regards

surya

former_member184752
Active Participant
0 Kudos

Excellent Document Umesh ,

Keep it up ,

Please keep us posted with your latest documents

Regard's

Tallha

UmeshMali4994
Active Contributor
0 Kudos

Hello Surya,,

Thanks for reviewing this document,,

Regards

Umesh Mali 

UmeshMali4994
Active Contributor
0 Kudos

Hello Tallha,,

Thanks for reviewing this document ,,,

Your compliment,Rating and like are  motivated me for posting more document,,

Regards

Umesh Mali

Former Member
0 Kudos

hello ,

umesh good thank you for this document

plz help me i want SAP PM full material.do have send me this mail:

suri403@gmail.com

Former Member
0 Kudos

hi Umesh
It was a very good document,
Thanks alot for drawing clear picture
regarding REM

iraladamodara_reddy
Active Participant
0 Kudos

good..

UmeshMali4994
Active Contributor
0 Kudos

Thanks Shreyas and Damodar.. :smile:

Regards

Umesh Mali

Former Member
0 Kudos

Thanks for sharing the document. It is very helpful for the beginners.

Regards,

Sk. S Alisha

UmeshMali4994
Active Contributor
0 Kudos

Thanks Alisha... :smile:

Former Member
0 Kudos

Dear Umesh,

Thank you very much for the document. I tried the scenario and got the result as well and now i am confident enough with respect to the REM process whereby i feel that i know some good initial knowledge in SAP PP

With best regards,

Sreenivas Nittala

michael_kozlowski
Active Contributor
0 Kudos

really a very valuable document

Best regards

Michael

jduppalapati
Participant
0 Kudos

Hi Umesh,

Thank You

Regards,

Jayadeep

Former Member
0 Kudos

Hi Umesh,

Very useful to understand the basic process of REM.

thanks a lot for documenting and sharing.

Regards,

Ravindhar m

former_member192506
Participant
0 Kudos

Amazing document umesh !

0 Kudos
Appreciated your effort Umesh.

Hope you'll post more documents in the future.

Thanks
JMEDINA
Participant
0 Kudos
Pretty good SAP PP REM process description. Regards ¡
UmeshMali4994
Active Contributor
0 Kudos
Hello Jerson,

Thanks for comment.. 🙂

Regards

Umesh Mali
sapires
Explorer
0 Kudos
Hello, trying to implement REM, but have one big problem with Costing, can you see at: here
0 Kudos
Please update it, sir

thanks for this document

 