INTRODUCTION

In this blog post you will learn about integration SAP PP PS with material component.

One of process integration between PP and PS is when you release a project structure (include Work Breakdown Structure, network, and material component) and it will be triggered to production planned order creation.

For detail process will be explained in Main section.

 

MAIN 

If we want to make integration process between SAP PP and PS, we can follow these steps =

  • Create project structure include project header, Work Breakdown Structure (WBS), Network, and Material Component (Tcode CJ20N)


 

  • Create WBS Bill of material (Tcode CS71).




 

 

 

  • Create Routing (Tcode CA01).In routing header select “material assignment” and input counter routing, material number, plant,and WBS element




 

  • Create cost estimate (Tcode CKW1) and Release cost estimate (Tcode CKW4)






 

  • Release Project ( Tcode CJ20N) and planned order is created automatically.


 

CONCLUSION

We can make integration process between SAP PP and PS with material component.

This process can be used for production based on project.

 

Thanks and regards

Anita A.

 
10 Comments
ibrahemy
Active Participant
Hello Anita,

Thanks for sharing ... keep it up

 

 

BR

Muhamed
anitaarifin04
Participant
0 Kudos
Hi Muhamed,

Thanks for feedback

 

 

Regards

Anita
former_member563743
Discoverer
0 Kudos
Hi anita

 

Thanks
former_member563743
Discoverer
0 Kudos
hello anita how will create production order ?

 

is reservation is planned order ???

i try to create production order from reservation in CO40 but get error planned order not found.

any different configuration for this specific.

 

please share end to end Documents if you have gaurav.jay.goyal@gmail.com

 

thanks in Advance

.
former_member563743
Discoverer
0 Kudos
is reservation is planned order ???

i try to create production order from reservation in CO40 but get error planned order not found.

any different configuration for this specific.

 

please share end to end Documents if you have gaurav.jay.goyal@gmail.com

 

thanks in Advance
Is there solution to run the CKW1 collectively?

I'm facing Make to Project scenario. Under a project, many make-level materials are assigned to the Network or the WBS element. I have to run the CKW1 one by one. It's boring.

If there is a transaction which I can run more than 1 material + WBS element, it would be useful.

Thanks in advance.

Linux Gao
0 Kudos
Hi,

Did you get the transaction? If yes the please also let me know the transaction it would be helpful for me.

 
0 Kudos
Hi Gaurav,

 

If you received the end to end documents then please also share it with me i will be grateful for you.

 

Regards

Sameed
Not yet. Now we have developed a Z-program to automatically run CKW1 in background.
mohammedrahman4
Explorer
0 Kudos

Thanks Anita . Do we need to assign only header material no i.e. P-100 to the network or all the components also of the BOM ? Where & how do we explode the BOM ?

Thanking you .

Mohammed