Hi SDN Gurus,
I came across below requirement from the client.
Client is in to business of manufacturing building material, where business requirement is
“Order Quantity” Will be in Pieces (PCs) and “Selling Price” will be in Cubic meter (M3),
which is nothing but Volume.
The same needs to be mapped in SAP.
While creating sale order, Customer requirement, is to have ONE Column for PCs and
ONE Column for Cubic Meter(M3) at Item Level.
So that,while creating sale order, if Customer increases Order Quantity (PCs) for a material,
Should automatically update relevant Volume /Cubic Meter (M3) of the respective material.
Note:
Production planning,to manufacture the material in pieces (PCs).
in pieces(PCs) and price not to be calculated on Pieces(PCs)
Eg: if 20 Piece=25.5 M3, then Sale order Item price, needs to be calculated for 25.5 M3 and
not for 20 Pieces.
Example of Material Description
Vertical Panel T200 W600 L3000
Dimension given in above material are in Millimetre (MM),
i.e.. Thickness 200MM / Width 600MM /Length 3000mm
T = Thickness / W =Width / L =Length
Solution to be mapped in SAP
One Column for PCs and One Column for Volume / Cubic Meter (M3),while creating sale order so that any change in Quantity ,should parallel y update respective Volume(Cubic meter(M3) for the material. |
Price for the material to be calculated on “Volume/ Per Cubic Meter(M3)" for ordered Quantity which is in Pieces. |
Proposed Solution in Standard SAP
(A) In Standard SAP, While creating material master record “Volume /Cubic Meter M3”
automatically calculated by giving dimension of the material.
Create material (T.Code:MM01) "Basic Data 1" Tab , we can see VOLUME field.
Standard SAP system automatically calculate “Volume /Cubic meter (M3)”, while entering
product dimension, In “Additional Data” as shown below.
Click Additional Data,Go to Unit of Measure TAB, and scroll to the right, to enter
product dimensions in Millimetre
Enter Product dimension (Length/width/thickness in Millimetre) and Press ENTER.
System will automatically calculate Volume (i.e.) Cubic Meter (M3) of respective dimension of the material.
Calculated Volume in Cubic meter (M3) can be seen in “BASIC DATA 1” tab, as shown below
(B) Now, Sale order Price to be calculated based on Volume in M3 for the respective material and
for calculated Volume for ordered quantity in pieces(PCs)
To Calculate, Price based on Volume, do the settings in calculation type for respective
Price condition type (Eg: ZPR0), as below.
T.Code : V/06
Create Sale Order (T.Code :VA01)
To have volume and Volume Unit, scroll to the right as highlighted above,
drag VOLUME and VOLUME UNIT, and SAVE it as a Variant as shown below.
Above screen shot displays, Volume and Volume unit in Cubic meter (M3) for one Piece (PC)
If we increase Order quantity (Piece), system parallel y updates the relevant volume, as shown below.
Now,while entering Price for the material, system needs to calculate Price per Cubic meter (M3),
for calculated volume for the ordered quantity in Pieces (PCs).
Entering Price with “ZPR0” Condition type
Double clicking condition type “ZPR0” to see calculation details
As explained above, user requirement had been mapped in standard.
Note: This is the first document im posting, looking forward for valuable feedback.
Regards
Jeeva