Dear Readers,
This Blog will cover End-End cycle including Important Configurations and Demo for PS Easy Cost Planning ( ECP ) Integration with S/4HANA Financial Planning
- As of Version 2022 FPS 00, SAP has provided out-of-box Integration of Project based cost planning integration with Financial Planning for Easy Cost Planning and Network Costing
- Before above mentioned version, we need to use Program (R_FINS_PLAN_TRANS_CO_ERP_2_S4H) to Transfer the value from Classical CO Table to ACDOCP Table
- With this new version, this manual step is reduced for Easy Cost Planning and Network Costing and now Data will be stored in ACDOCP Table along with Classical CO Table
- With This new feature, couple of Standard Fiori Apps of PS (Project Cost Report - Line Items, Project Cost Report - Overview) can be directly used as far as plan data is concerned.
- This New Feature is part of The Modernized Easy Cost Planning for projects and shall be available as part of S/4HANA perpetual scope
- In this Blog I will be explaining the Easy Cost Planning Integration with Financial Integration
- I assume Readers are aware of Function/Feature of Easy Cost Planning Method and S/4HANA Financial Planning , hence I will be focusing on subject itself.
Prerequisites :
- Necessary Configuration for Easy Cost Planning
- Maintain Category for Planning
- Assign Plan Category to CO Version for Easy Cost Planning for Project
Below are couple of important configuration screenshot.
- Maintain Category for Planning
- System Uses planning category to differentiate sets of plan data
- Usage 1 is defined for Easy cost planning for Project
- Assign Plan Category to CO Version for Easy Cost Planning for Project
- To Write Plan Data from ECP to Financial Integration ( CO Table to ACDOCP Table ) this is the new customization introduced
- This customization is based on CO Area and ECP CO Version
- Please, note that Once plan category is in use , you can not edit or delete it
Demo :
- Perform Easy Cost Planning for Project
- Check Values in ACDOCP Table
Summary
By using New Standard Configuration of S/4HANA 2022 FPS 00, we are able to Transfer Plan Cost from ECP to ACDOCP Financial Table along with Classical CO Table.
———————————————————————————————————————————-
Please, let me know if anyone have doubt or I missed something.
Your suggestions are most welcome.
Cheers for EPPM Community…!!!
Thanks,
Akash Khandelwal