Objective :
- To run the MRP for multiple plants.
- Same material involving into In-house production, External Procurement, Stock Transport Order and Subcontract process.
Plant Details:
- Plant B (Manufacturing Plant1)
- Plant C (Manufacturing Plant2)
- Plant B1 (Internal Warehouse for Plant1)
- Plant C1 (Internal Warehouse for Plant2)
- Plant A (Distribution plant)
Material Master Settings:
Plant | Plant A | Plant B1 | Plant C1 | Plant B | Plant C |
Material | Test 1 | Test1 | Test1 | Test1 | Test1 |
MRP Type | V1/V2 | PD | PD | PD | PD |
Reorder Point | 1000 | | | | |
Procurement Type | F - External Procurement | F - External Procurement | F - External Procurement | E – In house Production | E – In house Production |
Quota | Yes | Yes | Yes | | |
For Plant A:

Demand in Plant A :
Here ROP = 1000 number is act as demand.
When we run MRP system generates Stock transfer PR based on percentage given in Quota.
For Plant B1 and C1:

Demand Flow from different plants:

Total Demend in Plant (B and C) = Demand from Plant A + Demand from Plant B1 and C1
MRP Results:
When run MRP for Plant A:
Demand Created for Plant B1 and C1.

When run MRP for B1 and C1:
Create stock transfer dependent requirement from Plant A and create request for Plant B.
Create stock transfer dependent requirement from Plant A and create request for Plant C.

When run MRP for Plant B and C:
- Create stock transfer dependent requirement from Plant A based on Quota and Planned order will create based on Quantity + Dependent requirement from B1 and C1.
- If use any special procurement key for subcontract then SC PR will create based on Quota.
- Create direct PR or Scheduling Lines.