Material Resource Planning (MRP) | Master Production Schedule (MPS) |
MRP Plans materials / items those have dependent demand elements | MPS Plans materials / items those have only direct demand elements or independent demand elements |
During MRP Run, demand is flows down level elements because need to produce an item | During MPS, demand is flows direct from customer requirements or forecasted requirements |
MRP can be executed at FG/ SFG or multi-level also | MPS can be executed at FG level or first level only |
MRP recommended / Can be execute on daily to expedite items required to produce as per plan | MPS recommended run on weekly based on orders and forecast for that period / week |
Procedure: · Calculates net requirements for all the requirement quantities that are to be planned. · Calculates the quantity recorded in the procurement proposal according to the lot-sizing procedure · Procurement proposal: Materials procured externally, the delivery and release dates are determined, and for materials produced in-house, the production dates are calculated. · Materials produced in-house; the dependent requirements of the components are determined during the BOM explosion. · Additional requirements (unplanned goods issues, excess consumption of components in production, and so on) can be covered by using the materials forecast | Procedure: · Total planning run for master schedule items or single item planning for master schedule items · Creates dependent requirements for the BOM level directly below the planning level · Once the master plan has been finely tuned for the master schedule items, you start the total planning run for all dependent parts. |
Usage: In every industry for material planning | Usage: Mostly for FG products planning at Pharma, Automobiles, Chemicals, Food Industries. |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
3 | |
2 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |