Business Case
The company requires that procured materials are received at warehouse within specified shelf life. The material must have minimum 8 days of shelf life remaining at the time of goods receipt. The material has 20 days shelf life from date of manufacture. SLED requirement need to be confirmed during following cases:
In the event vendor provided goods do not match minimum shelf life requirement, warehouse would receive the goods as "GR blocked stock" (Mvt 103)
Material Master Setting
We are making following settings in Plant data view:
T-Code OMJ5
We need to activate both plant and movement type for SLED.
Plant
We have activated following plants for SLED:
Movement Type
We have activated following movement type for SLED:
MIGO
Vendor shipped the goods and we would receive the material against Mvt 101 with date of manufacture 08/20/2013 (MM-DD-YYYY)