Hi All,
Sometimes there can be a requirement where you might just want to refresh only master recipe or BOM but not both while copying the master data into a new process/production order. Enabling the check boxes in "Read master data " screen gives you the facility of refreshing either recent Master recipe or recent BOM or both.
We got a requirement of enabling the "New master recipe" and "New BOM" checkbox in "Read Master data " dialogue box of Tcode : COR2.
You can get this screen also by going to Tcode COR2 -> Process Order -> Functions -> Read Master data
We got a solution for this by re-setting the configurations in Tcode: COR4 .
- Goto COR4 , select the Plant and Order type for which you want to enable the checkbox
- Uncheck the checkbox "Approval Required"
I hope this blog would help people looking for such functionality .
Regards,
Twinkle Sahu