Calibration Process:
I had observed many queries related to calibration process steps,so please refer below which will support you. Thanks in Advance.
Master Data:
1.Create Equipment master-IE01
2.Create Task list -IA05
3.Create Maintenance plan-IP41
4.Schedule maintenance plan-IP10
Business Process :
Step-1 Deadline monitoring for maintenance plan (Transaction IP30)
Enter the Maintenance plan and click continue
Then the plan schedule and automatically tiger the calibration Order Scheduling status was show in Message text. Then go back
Step-2 To view Maintenance order (Transaction IW39)
List of calibration order are Display, Note the Order Number from the List which where you required
Step-3 Check & Release Maintenance order (Transaction IW32)
Step-4 Clear the Inspection lot (perform result recording & Usage decision) Transaction -QA32
Enter plant & Inspection lot origin-14 click F8 or execute
Step-5 Perform Result recording
Select Inspection lot line & click Results (pencil icon)
Enter & maintain the result
After entering result then valuate the same
Save the results.
Step-6 Perform the Usage decision for Inspection lot
Select the Inspection Lot click Usage decision (pencil icon)
Enter the UD code & Save
UD done
Step-7 Order confirmation (Transaction IW41)
Enter Order Number click Continue
Maintain the required Confirmation data.
Step-8 Technical Completion TECO order (Transaction IW32)
Enter Order Number
Continue
TECO & Save the order.
Note : while creating task list enter PM01 control key for Internal calibartion & PM02 or PM03 for external calibartion.
Thanks & Regards,
M.Arunkumar
SAP PLM Functional Consultant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
2 | |
2 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |