Former Member
19,933

Dear SCN Members

Most of the companies intend to apply budget to prevent over spending on assets purchased , which constitute major part of the companies annual expenditure.

this expenditure is classified under Capital Expenditure ..so all companies would put good control on both asset purchasing process and safe guard.

i will explain in this document how you can purchase an asset using preventive budget. there are two common scenario for asset purchasing using budget

- investment measure.

- Statistical Budget.

In this document i will focus on option no. 2

We have two available alternative to purchase the asset:

  • Purchase  asset first as asset under construction , and then capitalize after completion on related asset.
  • Direct Capitalization of asset.

To apply both scenario you have to follow both steps:

  1. Create Screen Layout for asset under construction & required asset classes that you intend to purchase asset and capitalize directly without accumulating  the cost and capitalize it in later  stages.

Menu Path: Spro-Financial Accounting (New)-Asset Accounting-Master Data-Screen Layout-Define Screen Layout for Asset Master Data

you choose the required asset classes ( or Asset under construction ) to activate cost order in the screen layout as below:

click on Logical Field Groups on the left screen and choose Time-dependent data and click on Field Group Rules,  then change the status of the cost order (21) from No to Opt ( Optional )

and click on both Main No and Sub no. to allow this field on both asset main and sub number.

repeat the above steps to all asset classes that you intend to use in this scenario when you will apply both options.

2. Create Asset Class ( Asset Under Construction ) allowing line item settlement

follow the menu path :

Spro-Financial Accounting (New)-Asset Accounting-Organizational Structures-Asset Classes-Define Asset Classes

T-code : OAOA

After creation on new asset under construction  classes.we will move to  MM area to activate the internal order field in account assignment A which will be used while asset purchasing.

T-Code : OME9

now you need to check you internal order configuration , if it has budget profile and apply statistical posting for asset.

Apply Statistical Posting T-Code OAK7 " Create cost element Type 90" or from KA01

Check your internal order budget profile

T-Code : KOT2

i will contribute another document describing how to create a budget profile and activate the availability control..

now to the configuration process has finished you now need to know how to apply the scenario

  • Create Internal order T-Code KO01
  • Assign Budget amount in the created internal order T-Code : KO22
  • Create Asset Under Construction T-code : AS01 and assign the internal order in the asset number in time dependent tab
  • Create Purchase requisition or purchase order on and use the account assignment A that will allow you to insert the asset number and internal order ..
  • try to create the PR / P.O with amount higher than the  budget limit .. you will have a message informing you that budget exceeded and you will not be able to save the PR/P.O
  • Settle the AUC to Final asset using T-code : AIAB

Hope this document will help to put more control on Asset purchasing procedures..

Practical Note:

if you are moving from the investment measure to the above scenario and keep the investment measure running till you finish the open orders related to it , you should not create cost element to the AUC GL for investment measure and create another AUC GL for the New cycle and create cost element Type 90 for it.

Regards

Mahmoud El Nady

40 Comments
waldo
Contributor
0 Kudos

Thank you very much for this doc.

Regards,

Oswald

Former Member
0 Kudos

Hi Osvaldo

Thanks for your valuable comment..

Regards

Mahmoud El Nady

Former Member
0 Kudos

Very good.

Congratulations on the document!

Artur

Former Member
0 Kudos

Thanks Artur for your postive feedback

regards

Mahmoud El nady

Former Member
0 Kudos

Teslam El Ayaadi     :wink:

Former Member
0 Kudos

Thanks Mr. Emad Hope it helps you..

Regards

Mahmoud EL Nady

Former Member
0 Kudos

Valuable knowledge.   Keep it coming.

Former Member
0 Kudos

Good and simple document.

Former Member
0 Kudos

Thanks Mr. Sudhir ...

Regards

Mahmoud El Nady

emad_gamal
Participant
0 Kudos

Really it's very helpfully , thanks alot mahomud

Former Member
0 Kudos

Hi Emad

Thanks for your positive feedback.

Regards

Mahmoud EL Nady

Former Member
0 Kudos

Thanks Mr. Mahmoud;

     Very helpful document where I was searching for such scenario to implement it at my customer site and it strongly fitted my requirement.

Best regards;

Former Member
0 Kudos

Hi Ahmed

Thanks for your encouraging feedback.

Regards

Mahmoud EL Nady

former_member186576
Contributor
0 Kudos

Thanks for sharing this wonderful document.

Former Member
0 Kudos

Hi Sam

Your feedback always valuable to me.. Thanks

Mahmoud EL Nady

Former Member
0 Kudos

Nice Document. Thanks a lot for sharing.

Former Member
0 Kudos

Hi Gidavari

You are welcome.. Thanks for your feedback..

Regards

Mahmoud EL Nady

former_member183690
Participant
0 Kudos

Hi Mahmoud EL Nady

Simply superb hope we get second document soon

Former Member
0 Kudos

Thanks for your encouraging Comment..

Regards

Mahmoud LE Nady

ibrahim-gad
Participant
0 Kudos

Very helpful demonstration,

I was looking for a document like this organized and clear. :smile:

We are using the same scenario in addition to fund management.

So, by combining them we can control asset class "FM" and the asset itself "IO". :cool:

Thanks again and looking forward to your upcoming Doc.

Ibrahim

Former Member
0 Kudos

Thanks ibrahim .. your feedback is much appreciated. . also you udea about combining FM with budget control will impose more control option to assets acquisition process. .

Regards..

Mahmoud el Nady

Former Member
0 Kudos

Nice document. It is really helpful.

Former Member
0 Kudos

Thanks Chirag for your positive feedback.

Regards

Mahmoud L Nady

former_member183349
Active Participant
0 Kudos

Good document information and easy understandable.

Regards,

Vivek

Former Member
0 Kudos

Hi

Thanks Vivek for your encouraging feedback..

Regards

Mahmoud EL Nady

Former Member
0 Kudos
Very good document, Thanks
Former Member
0 Kudos

Thank you very much Adityaz..

Regards

Mahmoud

Former Member
0 Kudos

Hello Mahmoud,

firstly am appreciating you to take initiation to have this document.

and also kindly let me know how purchase an asset with investment measure and what are the prerequisites to do for AUC with Investment measure.

If possible send it to      arunsap@outlook.com

Regards

Arun

Former Member
0 Kudos

Hi

Thanks Arun for your positive feedback.. if you would like to know the investment measure steps , you may refer to below document

SAP Best Practices Baseline Package

document 164

Regard

Mahmoud EL nady

Former Member
0 Kudos

Hello Mahmoud,

Very Good document. Just one clarification, if we are to use budget check against WBS and asset capitalization via the same, the only change would be that instead of internal order, we are utilizing WBS field in AS01 and WBS related budget profiles for checking the budgets. Is it right?

Former Member
0 Kudos

Hello Mahmoud,

Thanks for the information. As i just know the process of asset procurement but when am executing in system getting different issues. the asset cycle ( through MM ) which am doing is

1) PO with Acc assignment 'A' by entering asset number.

2) Goods Receipt

3) Asset Transfer from warehouse AUC  Project AUC

4) Settlement Execution AIAB

5) Dep run

For the above process i need a back end configuration.

Could you please assist me for executing the above process.

will be more thankfull...

Regards

Arun

Former Member
0 Kudos

Hi Parshanth

Thanks for your positive comment.. I am not able to tell you that if you use WBS it will give you same result , but it seems logically possible ..you may try iy and feed us back with the result ..

Thanks

Mahmoud

Former Member
0 Kudos

Hi Aurn

i believe that me document is covering your mentioned required steps .. could you try it and inform me back if it work successfully with you or not?

Regards

Mahmoud EL Nady

Former Member
0 Kudos

Hello Mahmoud,

Ok sure. will revert you back if i get any queries..

Thanks

Arun

Former Member
0 Kudos

Hi

Nice document. Thanks for beautiful explanation.

Regards

Karthi

Former Member
0 Kudos

Hi

Thanks for your Positive Feedback..

Regards

Mahmoud

heba_okby
Explorer
Really l proud because i work with you
Former Member
0 Kudos
Hi Heba

Thanks so Much .Appreciated .

Regards

Mahmoud
0 Kudos
its very helpful document and explanation is so clear.

Thank you so much sir for this document.