Enterprise Resource Planning Blog Posts by SAP
cancel
Showing results for 
Search instead for 
Did you mean: 
Markus_Oertelt
Product and Topic Expert
Product and Topic Expert
7,108

We are constantly enhancing the MRP apps so that production planners can evaluate the MRP results with the following FIORI apps: 

  1. Monitor Material Coverage - Net Segments (F0247A)

  2. Monitor Material Coverage - Net and Individual Segments (F2101A)

Here are the details of the latest innovations. Check out the enhanced the SAP Fiori look & feel with its real-time data evaluation. With that you will have your planning situations always under control. 

In total we enhanced the apps with the following additional columns, navigations and colorings:

Overview_1.jpg

If you are interested in the details continue to read below. 

Master Data Issues 

If master data issues are detected for a material during an MRP run, the number of issues is displayed in this column:

Master_Data_Issues_1.jpg

By clicking on the link, you can check the number of warnings, errors, and cancellations that have been identified, and navigate to the Display MRP Master Data Issues app to display detailed information and solve or accept the issues as required. 

Master_Data_Issues_2.jpg

When you navigate to the Display MRP Master Data Issues app, the list of master data issues is filtered automatically according to the category and the respective material that you selected (in my case I selected "Errors"): 

Master_Data_Issues_3.jpg

Past Due Elements 

This column displays the number of receipt elements in the stock / requirements list that have an opening date, a basic start date / release date, or a basic end date / delivery date in the past:

Past Due Elements 1.jpg

Depending on the type of an MRP receipt element, different dates can be defined to specify when an open quantity is planned to be delivered. For example, a planned order has an opening date, a basic start date, and a basic end date, while a purchase requisition has a release date and delivery date assigned. To determine the number of past due elements, the system adds up the following MRP elements:

  • Receipt elements that have an opening date in the past

  • Receipt elements that have a basic start date or release date in the past

  • Receipt elements that have a basic end date or delivery date in the past

The sum of these elements is displayed in this column to help you determine whether actions are required to make sure all requirements from the last MRP run can be fulfilled.

Important to know is that production orders or process orders that have a basic start date in the past, but a basic end date in the future are not considered for this column, because a start date in the past is not classified as an exception for these types of MRP elements.

Opening Day in Past 

This column displays the number of receipt elements in the stock / requirements list that have an opening date in the past:

Opening Date in Past.jpg

The opening date of a receipt element is the date at which a procurement proposal (purchase requisition or planned order) should be converted into a purchase order or production order / process order. The responsible MRP controller can use the period between the opening date and the start date to complete the conversion. 

The system automatically counts the number of receipt elements with an opening date in the past and displays it in this column. This helps you determine whether actions are required to make sure the requirements that were determined during the last MRP run can be fulfilled.

Important to know is that for this column, the system only counts receipt elements that do not have a basic start date or a basic end date in the past. Receipt elements with a basic start date or a basic end date in the past are added to the counter in the Start Date in Past and End Date in Past columns, respectively.

Start Day in Past 

This column displays the number of receipt elements in the stock / requirements list that have a basic start date or release date in the past: 

Start Date in the Past.jpg

The start date or release date of a receipt element is the earliest date at which the production or delivery of an ordered quantity can start. A start date in the past might indicate the conversion is already too late. In the example above it is one; therefore, the system indicates that we have one receipt element with a basic start date or release date in the past.

This is important for the production planner to help determine whether actions are required to make sure the requirements that were determined during the last MRP run can be fulfilled. Important to know is: 

  • For this column, the system only counts receipt elements that do not have a basic end date or delivery date in the past. Receipt elements with a basic end date in the past are added to the counter in the End Date in Past column. 

  • The opening date in the past is also not calculated. Always the worst possible past due date is counted.

  • Production orders and process orders are not taken into account for this column, because a start date in the past is not classified as an exception for these MRP element types.

End Date in Past 

This column displays the number of receipt elements in the stock / requirements list that have a basic end date or a delivery date in the past: 

End day in Past.jpg

The end date or delivery date of a receipt element is the latest date at which an ordered quantity must be available. If we look at material FIO-TSC-ACC0007 then we see four elements that have an end date in the past: 

End day in Past_2.jpg

The system automatically counts the number of receipt elements with a basic end date or delivery date in the past and displays it in this column. This helps you determine whether actions are required to make sure the requirements that were determined during the last MRP run can be fulfilled.

Rescheduling Proposals 

Companies want to avoid supply shortages or excess supply; therefore, they need to be able to reschedule receipt elements to an earlier date to prevent material shortages or to a later date, for example, if requirements are postponed. Furthermore, enterprises need to be able to cancel receipt elements if they are no longer required:

Rescheduling Proposals.jpg

This is really easy to do now and you will find all the details in this Blog Post: Manage Supply Shortage and Excess Supply with MRP ... - SAP Community

Note

This column indicates whether a material note exists for a material:

Note.jpg

For each material, you can create a material note to provide additional information to production planners. If a note exists for a material, Yes is displayed in this column. You can see the message of the note in the Manage Material Coverage app: 

Notes_1.jpg

With this it is really easy for the Production Planner to leave additional planning comments regarding the material.  

Day's Supply (Working Days)

As a production planner, you can use days' supply information to evaluate the current planning results for a selected material. Based on the current stock and the receipt and requirements information included in the stock / requirements list for a material, the system determines the day of the first shortage and displays the number of working days until the shortage occurs in this column:

Days Supply.jpg

For shortages that occur in the future, the system counts the number of working days that can be fully covered and displays it as a positive value. Neither the current date nor the day of the first shortage are taken into account for this calculation.

 

Days Supply 1.jpg

For shortages that occur today or in the past, the system counts the number of working days between the day of the first shortage and the current date and displays it as a negative value. The day of the first shortage and the current date are taken into account for this calculation, that is, a shortage that occurs today results in a days' supply value of -1.

 

Days Supply 2.jpg

The values displayed in this column can differ according to the shortage definition that you select.

For materials with time-dependent safety stock levels, the system automatically compares the number of working days determined as days' supply with the Safety Days of Supply (Safety DOS) and Target Days of Supply (Target DOS) values that are defined in the Maintain Time-Dependent Stock Levels app for the current date. The definition can be done material specific and time-interval specific: 

Maintain Time Dependent Stock Levels.jpg

 Based on the result of this comparison, it adapts the coloring of the days' supply value as follows:

  • If the number of working days until the first shortage is below the safety DOS, the value in the Days' Supply column is highlighted in red.

  • If the number of working days until the first shortage is equal to the safety DOS or between the safety DOS and the target DOS, the value in the Days' Supply column is highlighted in green.

  • If the number of working days until the first shortage is equal to or above the target DOS, the value in the Days' Supply column is highlighted in yellow.

Days Supply 3.jpg

The reason behind the coloring is to avoid shortage situations (below safety stock) and highlight the overstock (over target). The goal for the planner is to keep the inventory on the green level between safety and the target. 

The color coding is applied to all materials within the Maintain Time-Dependent Stock Level app, regardless of the safety stock method selected in planning or whether the time-dependent values are factored into the planning process.

Stock Day's Supply (Working Days)

Displays the number of working days that can be fully covered before a shortage occurs for the selected material, based on its current stock. Planned receipts are not taken into account:

 

Stock Days Supply.jpg

As a production planner, you can use stock days' supply information to evaluate the current planning results for a selected material. Based on the current stock and the requirement information included in the stock / requirements list for a material, the system determines the day of the first shortage and displays the number of working days until the shortage occurs in this column:

  • For shortages that occur in the future, the system counts the number of working days that can be fully covered and displays it as a positive value. Neither the current date nor the day of the first shortage are taken into account for this calculation.

Stock Days Supply 2.jpg

  • For shortages that occur today or in the past, the system counts the number of working days between the day of the first shortage and the current date and displays it as a negative value. The day of the first shortage and the current date are taken into account for this calculation, that is, a shortage that occurs today results in a stock days' supply value of -1.

Stock Days Supply 1.jpg

The values displayed in this column can differ according to the shortage definition that you select.

The same dependencies apply also here with the Maintain Time-Dependent Stock Levels app for the current date. 

  • If the number of working days until the first shortage is below the safety DOS, the value in the Stock Days' Supply column is highlighted in red.

  • If the number of working days until the first shortage is equal to the safety DOS or between the safety DOS and the target DOS, the value in the Stock Days' Supply column is highlighted in green.

  • If the number of working days until the first shortage is equal to or above the target DOS, the value in the Stock Days' Supply column is highlighted in yellow.

Stock Days Supply 3.jpg

Intraday Supply (Working Days) 

Displays the number of working days that can be fully covered before a shortage occurs for a material, plus two decimal places to indicate which fraction of the requirements on the day of the first shortage can be covered by the available quantity from the previous day. The intraday supply is determined based on the current stock and the receipts and requirements information included in the stock / requirements list for a material.

Intradays Supply.jpg

As a production planner, you can use intraday supply information to evaluate the current planning results for a selected material. The value displayed in this column includes the following information:

  • Days' supply: the number of full working days until a shortage occurs

Intradays Supply 1.jpg

 

  • Fractional coverage of the requirements on the day of the first shortage: fraction of the requirements that can be covered by the available quantity from the previous day. It is calculated by dividing the available quantity by the aggregated days' demand.

    The system determines the value for this column based on the following formula: Intraday Supply = Days’ Supply + Fractional Coverage on the Day of the First Shortage.

The value displayed in this column can differ according to the shortage definition that you select.

 

For materials with the values defined in time-dependent safety stock levels (MTDSL) for the current date, the system automatically compares the number of full working days until the first shortage (days' supply) with the Safety DOS and Target DOS values that are defined in the Maintain Time-Dependent Stock Levels app for the current date. Based on the result of this comparison, it adapts the coloring of the intraday supply value as follows:

  • If the number of full working days until the first shortage (days' supply) is below the safety DOS, the value in the Intraday Supply column is highlighted in red.

Intradays Supply 2.jpg

  • If the number of full working days until the first shortage is equal to the safety DOS or between the safety DOS and the target DOS, the value in the Intraday Supply column is highlighted in green.

Intradays Supply 3.jpg

  • If the number of full working days until the first shortage is equal to or above the target DOS, the value in the Intraday Supply column is highlighted in yellow.

Intradays Supply 4.jpgThe coloring of the intraday supply value is determined based on full working days. The fractional coverage on the day of the first shortage is not taken into account. So, the coloring is the same as for Days Supply. 

Stock Intraday Supply (Working Days)

Displays the number of working days until a shortage occurs for a material, plus two decimal places to indicate which fraction of the requirements on the day of the first shortage can be covered by the available quantity from the previous day. The stock intraday supply is determined based on the current stock and the requirements information included in the stock / requirements list for a material. Planned receipts are not taken into account.

 

Stock Intradays Supply.jpg

As a production planner, you can use stock intraday supply information to evaluate the current planning results for a selected material. The value displayed in this column includes the following information:

  • Stock days' supply: the number of full working days until a shortage occurs, based on the current stock of a material

Stock Intradays Supply1.jpg

  • Fractional coverage of the requirements on the day of the first shortage: fraction of the requirements that can be covered by the available quantity from the previous day. It is calculated by dividing the available quantity by the aggregated days' demand.

    The system determines the value for this column based on the following formula: Stock Intraday Supply = Stock Days’ Supply + Fractional Coverage on the Day of the First Shortage.

The value displayed in this column can differ according to the shortage definition that you select.

For materials which have values defined in the time-dependent safety stock levels, the system automatically compares the number of full working days until the first shortage (stock days' supply) with the Safety DOS and Target DOS values that are defined in the Maintain Time-Dependent Stock Levels app for the current date. Based on the result of this comparison, it adapts the coloring of the stock intraday supply value as follows:

  • If the number of full working days until the first shortage (stock days' supply) is below the safety DOS, the value in the Intraday Supply column is highlighted in red.

Stock Intradays Supply2.jpg

  • If the number of full working days until the first shortage is equal to the safety DOS or between the safety DOS and the target DOS, the value in the Intraday Supply column is highlighted in green.

Stock Intradays Supply3.jpg

  • If the number of full working days until the first shortage is equal to or above the target DOS, the value in the Intraday Supply column is highlighted in yellow.

Stock Intradays Supply4.jpg

The coloring of the stock intraday supply value is determined based on full working days. The fractional coverage on the day of the first shortage is not taken into account. Also here the same principal as for Stock days supply. 

Don’t hesitate to leave a comment and check out our new community page to ask your questions and engage with the experts. Follow the PSCC_Enablement tag to stay up to date with our latest blog posts.

Follow us on @SAP and #S4HANA, and myself on LinkedIn . 

 

Markus_Oertelt_0-1718783807378.png

Watch Our Live Sessions

In January 2024, we hosted a series of 19 compelling live sessions to highlight the exciting innovations shipped with the SAP S/4HANA Cloud Public Edition 2402 release. Missed the live sessions? No problem! Take advantage of the entire series or pick and choose the sessions most relevant to you on demand.

Markus_Oertelt_1-1718783807404.png

Inside SAP S/4HANA Cloud

There is no customer success without project success and product success! Leverage the unique knowledge and expertise of SAP S/4HANA Cloud experts, partners, and customers, sharing their SAP S/4HANA Cloud implementation project best practices and lessons learned – anywhere, anytime. In this podcast, we give you all ingredients to get to the next level and make your SAP S/4HANA Cloud project a success. Subscribe now and benefit from the shared knowledge!

Markus_Oertelt_2-1718783807393.png

openSAP Microlearnings for SAP S/4HANA Cloud

Our openSAP microlearnings for SAP S/4HANA Cloud offer an exciting new learning opportunity. What began with a small batch of 20 videos, has now become a channel with more than 50 microlearnings that have generated over 20,000 views. Today, we cover multiple lines of business such as finance, manufacturing, and supply chain management, and key technology topics like Master Data Management, extensibility, SAP User Experience, and upgrade management. We are continuously adding new microlearnings to our channel, so make sure you check them out.

Markus_Oertelt_3-1718783807457.png

Your Voice Matters

You want to learn more and actively engage with SAP subject matter experts on SAP S/4HANA Cloud topics? We have just the right place for you! Join our interactive community where we bring together customers, partners, and SAP experts with a clear mission: To engage with one another about best practices and product solutions. We invite you to explore the ‘one-stop shop’ as the central place for all resources, tools, content questions, answers and to connect with experts who will guide you through your journey to the intelligent, sustainable enterprise.

Markus_Oertelt_4-1718783807458.png

Find All of Our Assets

SAP S/4HANA Cloud is the foundation of the intelligent, sustainable enterprise and is an innovative, robust, and scalable ERP. We at Cloud ERP Product Success and Cloud Co-Innovation offer a service as versatile as our product itself. Check out the numerous offerings our team has created for you below:

Markus_Oertelt_5-1718783807444.png

 

Markus_Oertelt_6-1718783807458.png

Where to Find More Information:

 

 

4 Comments