This blog explains about one of the new features from QM module i.e., “Problem solving process through 8D methodology”, Which is available in in S/4 HANA 1909 and S/4 HANA 2020 as well.

When we implement QM module for automobile industry, the most common ask from business is to map 8D methodology in SAP. Since we do not have direct solution in standard SAP either we do custom development or we do work around by defining tasks and activities in quality notifications. Now SAP came up with feature called “Non-conformance management” which deals with defects recording and investigation for that defect either through traditional Quality notifications or with 8D methodology.

What is 8D methodology?

The eight disciplines (8D) model is one of the problem solving approach typically employed by quality engineers. It is most used by the automotive industry however it has been successfully applied in healthcare, retail, finance, government and manufacturing.

The purpose of the 8D methodology is to identify, correct, and eliminate recurring problems, making it useful in product and process improvement. The 8D problem solving model establishes a permanent corrective action based on statistical analysis of the problem and focuses on the origin of the problem by determining its root causes. Although it originally comprised eight stages, or disciplines, the eight disciplines system was later augmented by an initial planning stage.

How to use 8D methodology?




  • D1: Use a team - Select and establish a team of people with product/process knowledge.

  • D2: Define and describe the problem- Specify the problem by identifying in quantifiable terms the who, what, where, when, why, how, and how many (5W2H) for the problem.

  • D3: Develop interim containment plan; implement and verify interim actions- Define and implement containment actions to isolate the problem from any customer.

  • D4: Determine, identify, and verify root causes and escape points- Identify all applicable causes that could explain why the problem occurred. Also identify why the problem was not noticed at the time it occurred by using 5 whys and cause and effect diagram to map causes against the effect or problem identified.

  • D5: Choose and verify permanent corrections (PCs) for problem/nonconformity- Through preproduction programs, quantitatively confirm that the selected correction will resolve the problem for the customer.

  • D6: Implement and validate corrective actions- Define and implement the best corrective actions (CA).

  • D7: Take preventive measures- Modify the management systems, operation systems, practices, and procedures to prevent recurrence of this and all similar problems.

  • D8: Congratulate your team- Recognize the collective efforts of the team. The team needs to be formally thanked by the organization.


 

How 8D methodology works in S/4 HANA?

When any defect identified by Quality technician or Quality engineer, they will create defect by using “Process defects” fiori app and upload the relevant documents and picture if required.


In this app, we have option to two option for problem solving for the created defect under “problem solving process tab” Here you can choose one of the below options.

  1. Quality tasks

  2. 8D methodology.


Once you select 8D methodology, you can get below format as like legacy 8D format. Here you can eight disciplines. Initially all tasks will have status “Not started”. Once you start the task you can change the status to “In process” and then you can change to “complete” once it gets completed.


 

During this process, you can define the root cause in D4, can define task for corrective action with respect to root cause in D5, can implement task and can be assigned, which was defined in earlier stage in D6 and can perform prevent actions in D7.

 



 


 

Once step get completed, update the status as “Completed” so that status can be monitored. By this way you can perform 8D steps by using standard SAP functionality.

 


 

This functionality available only in fiori that means this feature is not available in GUI. By using this functionality, we can map 8D methodology requirement in SAP without any custom development or without any work arounds.

 

Thanks & Regards

Hanumantharao.C

SME-PP/QM
10 Comments
Ruthvik_Chowdary
SAP Champion
SAP Champion
0 Kudos

Great Explanation!!

8D comes with the same licence as S/4HANA or extra Licence is required? 
available on cloud or On-premises?

former_member651353
Participant

ruthvik.chowdary2 ,

Its standard functionality of QM available in S/4 HANA 1909 and 2020 on premise. No need of additional license.

former_member743727
Discoverer
Defects are used in inspection lot. Is there any relation with defect that is recorded in QF01 at the characteristics level of an inspection lot.

It's normal that defects in inspection lot (QF01) are not getting displayed in the tile "Nonconformance analytics" and "manage defect"
0 Kudos

Hi,

thanks a lot for sharing!

I am sharing the concern of Omar Bakkali: this seems to work only for defects created from the app "Process Defect", not for defects created from inspection lots or from QM notifications. Is there a particular configuration to perform ?

By the way: do you know in which table are stored those defects created from "Process defects" ? 

Thanks for your help!

ITUSER
Explorer
0 Kudos
hello ,

Please how can we have the 8Ds complete in PDF ?
chanba1
Discoverer
0 Kudos
Hi Théo,

 

I am asking myself the same question. We activated and customized the App. The functionality is wunderful, but without the ability to print the "killer-application" is somewhat missing...

 
Minerva
Newcomer
0 Kudos

Hello experts,

Could you let me know how BP for D1 team must be created? I'm unable to display BP list in matchcode.

 

Thanks in advanced.

Rangaa
Participant
0 Kudos

I need to assign the role to partner in D1 team ? How can i do that ? 

Rangaa
Participant
0 Kudos

Hi I want to create a 8D team. 

I am trying to assign the partner in D1 Step, However how i can add the team member in list. I can only see some Bussiness partners in the list and not all, Is there any specific role which needs to be assign to parter to get display in the partner list ?

Lziel
Explorer
0 Kudos

Hey,

is it possible to generate the 8D report as a PDF in SAP S/4HANA version 1909?

Thank you!