Hi All,

We have a scenario where our customer is looking for a new functionality which can be developed only in a Partner Development Tenant environment. The below question has got the exact scenario that we would like to develop for the business.


https://answers.sap.com/questions/13055225/moving-a-solution-from-a-partner-development-tenan.html

The current system is already live and our existing landscape has got integrations with SAP ECC. Below image gives more details about the existing landscape:

We are looking to add a new functionality via SDK (for which partner development tenant is mandatory. Currently, we only have 'Test' tenants) and below is the landscape we may have moving forward:
Development, QA, Pre Prod >> Test Tenants
Production >> Production Tenant
In addition to this, we are going to build the new functionality in the 'Partner Development Tenant'

Questions around this:

1. What are the implications of moving to the new landscape that is planned?

2. Please list all the limitations, considerations and pre-requisites of moving to this new landscape.

Thanks,
Krishna

Accepted Solutions (1)

Accepted Solutions (1)

cianbarrett
Active Participant

Hi Krishna,

Once a Partner Development Tenant is provisioned, it behaves much the same as an additional Test Tenant. Two main points to consider:

  1. The Switch Customer functionality is enabled and you must ensure that the Customer ID is maintained correctly. Otherwise you will not be able to deploy your Solution 2 to the Customer Test Tenant.
  2. Patches for Solution 2 should only be created on the Partner Development Tenant.

Hope this clarifies your query.

EDIT: This is only available as part of SAP Business ByDesign