The schedule line’s date is depending on the requested start date of the service order.

SAPSupport
Employee
Employee
0 Kudos
1,018

When creating and planning a service order with spare parts, the schedule line’s date is always the creation date of the service order but not depending on the requested start date or any other date. So the is no possibility to change the date of the schedule line, which is transferred to the material reservation.
------------------------------------------------------------------------------------------------------------------------------------------------
Learn more about the SAP Support user and program here.

Accepted Solutions (1)

Accepted Solutions (1)

SAPSupport
Employee
Employee
0 Kudos

Dear customer

add the date type REQ_DLV_DATE in your date profile (item) as it's explained in KBA

3298041 - Schedule line : how to update the field Date Requested

Best regards

Silvia Ventura

AndreasHammer
Explorer
0 Kudos

Hi Silvia,

I've implemented the mentioned note within customizing, adding the REQ_DLV_DATE in the date profile of the spare part item. I can select the date within the dates section of the item, however the schedule line of the item does not update or use the date I've provided. Any other ideas?

Thanks and best regards

Andreas