on ‎2018 Feb 06 3:28 PM
Hi all,
I tested the resource scheduler today (release 1802). So I released an item in a ticket for scheduling and wanted manually to assign the demand per drag&drop. But I cannot see the service technicians in the calendar view on the right half of the resource scheduler view, although I selected a service team in the filter.

Some tips what to do that I see the service technicians again? Does someone experience the same issue?
Best regards,
Deborah
Request clarification before answering.
No Service Technicians are shown in the Calendar view, if the working hours for the Service Technicians are not maintained.
To maintain the working hours for the Service Technicians, please follow these steps:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi anshika.goyal,
the business role has just access restrictions for employee, products and accounts. But the Work-Center Resource Scheduler - View: Assignments has not yet been assigned. So I tested it with assigned WC view assignments, but I still cannot see the assignment in the service technicians' calendar...
What is the release flag for assignments? I read something about this in the documentation. Where do I set the release flag in the assignment (actions button in assignments is greyed out) and is it important for visibility in the calendar?
Thanks Anshika,
Best regards, Deborah
Hi Deborah,
If there is a need to restrict editing of an assignment, you can use the release flag for this purpose (by setting up a configuration).
However, this does not impact the visibility in the calendar. Need more details to check why you cannot see the assignments in the calendar. Please provide the sequence of steps that you performed, whether testing in HTML5 or Fiori Client (RUI), which browser and any other relevant details such as user role etc. Are you checking in the work center 'Calendar' or in the resource scheduler gantt chart? Is this an issue with only one assignment or all the assignments that you have created? If not already done, please create more assignments and check. Another thing you can check is if the assignment is in lifecycle status canceled, then it will not be shown.
Regards,
Anshika