Material Replication error after SPS update

former_member603059
Participant
0 Likes
851

Hi Experts,

We recently did an SPS update and are getting the following error after a mass change to material master:

Sales unit EA is not assigned to this product. Message No. CRM_PRODUCT_SALES030.

All unit of measures have been checked and they are assigned properly for both Base and Alternative. We did a mass change of the Prod. stor. location on the material master. Nothing with the Unit of Measure.

The SPS has only been applied in our DEV environment. As a test we made the same mass change in our Quality environment where the SPS has NOT been applied yet. Replication worked without issue. No error messages.

Anyone have any suggestions or notes we can apply to fix our issue?

Here's our pre and post SPS status:

Pre SPS Version
EHP3 FOR SAP CRM 7.0 EHP3 FOR SAP CRM 7.0 11 (01/2016) sap.com EHP3 FOR SAP CRM 7.0
SAP CRM 7.0 17 (06/2015) sap.com SAP CRM 7.0 / NW7.01
SAP NETWEAVER 7.4 13 (11/2015) sap.com SAP NETWEAVER 7.4

Post SPS Version
EHP3 FOR SAP CRM 7.0 EHP3 FOR SAP CRM 7.0 21 (03/2021) sap.com EHP3 FOR SAP CRM 7.0
SAP CRM 7.0 23 (02/2021) sap.com SAP CRM 7.0 / NW7.01
SAP NETWEAVER 7.4 25 (12/2020) sap.com SAP NETWEAVER 7.4

Accepted Solutions (1)

Accepted Solutions (1)

Rene_M
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi,

please check if SAP note

3058043 - Error in replication of material ERP -> CRM

is implemented - this note should solve this error normally.

Thanks

Rene

former_member603059
Participant
0 Likes

Thanks Rene. This did resolve our issue.

Appreciate the information.