iDocs processing sequence for product-variant (multi-dimensional) set up with single MATMAS

sobha
Explorer
0 Kudos
196

Hi,

Below iDocs are sent from SAP to Hybris (1811).

  • CHRMAS
  • CLSMAS
  • MATMAS/CLFMAS

We need MATMAS to be processed before CLFMAS as we have customized saperpproduct-target XML set up to create a base product and variant product for the incoming material number in MATMAS - incoming material number becomes the variant product code upon processing and we have to load product features on to the variant product.

CLFMAS processing needs to be done after MATMAS iDoc is processed so that base and variant products are created correctly and class attributes are loaded correctly on to the variant product.

Is there a way to ensure MATMAS is processed prior to CLFMAS processing?

Thank you,

Sobha Tammana