on 2024 Jul 03 9:34 AM
Hi!
I'm using SAP Business One 10.0 (10.00.180) FP 2111 and I'm encountering issues with due date calculations(AR Invoice). Specifically, I want to exclude weekends from these calculations. Here’s what I’ve done so far:
Despite these configurations, weekends are still being included in the due date calculations. Could you provide any insights or solutions to resolve this issue?
Request clarification before answering.
Hi,
Try to assign holidays in Business Partner Master Data >>> Payment Terms tab >>> Holidays
Hope this helps,
Son Tran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear @esleonardo ,
If I remember correct, the holidays works on MRP and in the marketing documents.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.