cancel
Showing results for 
Search instead for 
Did you mean: 

[ChaRM] Need to change change cycle assignement in mass

Slimdre
Discoverer
0 Kudos
133

Hi experts,

We are using cCTS in ChaRM and I have a need to be able to change, in mass, the Change Cycle assignement of several Change Documents just before the move into production. I'm able to change the cycle in Charm with the option 'Change Cycle Assignement' but I have a requirement to be able to do it in mass. In standard, I don't found any report/function to do it. We are using the SAP Sol. Manager 7.2. I found this FM '/TMWFLOW/CRM_CHNG_DOC_REASSIGN' but it's now obsolet... Someone has an idea?

 

View Entire Topic
DoloresCorrea
Product and Topic Expert
Product and Topic Expert

Hello Slimdre

There was never a report to change from an active cycle to another active cycle. Report /TMWFLOW/CRM_CHNG_DOC_REASSIGN was used to assign changes in closed cycle to a followup active cycle from the same project.

But in 7.2 the concept has been completely redesigned hence the report /TMWFLOW/CRM_CHNG_DOC_REASSIGN is not longer needed.

Customer must assign changes manually in CRM UI. There is no other way to do that.

You can refer to below document.

https://help.sap.com/viewer/8b923a2175be4939816f0981b73856c7/7.2.10/en-US/4c4da0c3b5c76f82e10000000a...

Best regards,

Dolores

Slimdre
Discoverer
0 Kudos

Thx for this answer but I'm really surprise to don't a way to do it in mass. As a cycle is following an iteration, a project or a milestone, we should be able to have the possibility to change in masse the change cylce... And this option exist in CRM UI... In fact, our intention is to be able to change the cylce just before the MiP in order to import in a different timeslot with automatic job import.