on ‎2018 Sep 11 7:52 AM
Hi,
I have set up an workticket integration C4S <> ECC.
In the quick guide i read the following.

The internal order is created as wel as my debit memo request, but the internal order numer is not displayed in my debet memo request.
What setting makes this happen? Can't find it in the documentation.
KR
MJ
Request clarification before answering.
Hi Marie,
You need to overwrite the Business Transaction event for the CRM-CO integration in this case to ensure that the internal order is assigned in the account assignment tab for the debit memo.
Procedure
Access the below transaction or navigate to the following IMG menu:
Transaction CodeFIBFSAP ERP IMG MenuSales and Distribution -> System Modifications -> Communication SetUp ->Business Transaction Events



Regards,
Ashish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I created a message for SAP and they responded with the following:
1) Activate NDE : This is done in your system.
2) If using the BADI implementation for "BADI_COD_ERP_SERVICE_CONF" and setting any X Flags for CS_Header in the method MAP_SD(IF_BADI_COD_SERVICE_CONF~MAP_SD) then you need to also set all the relevant fields in the BADI which are being set in CL_COD_SD_REP_HELPER=>ADJUST_HEADER since these are skipped while processing.
=> I see you are using this BADI and you need to update the codeline accordingly.
Will update once this is fixed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the feedback. I will keep you (all) posted.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahmoud,
May be then the best thing to do is to log an incident.
Kr.
MJ
Thank MJ for the suggestion, the issue has been resolved by following Ashish steps but it was missing the last step to Activate NDI New Dimension Integration.
Attached the
Thank you, Mahmoud. I saw your posting and did that also.
Pls let me know if I need to verify something else. Appreciate your help.
Hi Jameel,
The CODERINT package is now to the highest level, but still the internal order is not filled in the debet memo request field. Is ther any post processing needed?
KR
MJ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi MJ,
Apologies for the late reply. There isn't really any specific post processing needed. What I mean is, it should be working without the need for any additional ABAP. Probably best to create an incident from C4C so our support guys can look into it. You can use the component LOD-CRM-INT-ERP. I suspect there is an additional activation needed in ERP to allow the IO to display in the DMR which the support colleagues can confirm.
Regards,
Jameel
Hi MJ,
We sometimes see this on our projects.
Have you checked if the latest CODERINT package is installed in ECC with the latest SP version? Usually this solves the issue.
Hope that helps
Jameel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.