Updating Reference Date while completing PM notification

former_member210730
Participant
0 Kudos

Hi,

I need to update the reference date of the PM notification, is there any BAPI or FM available please advice.

Thanks

Vinay

4 REPLIES 4

custodio_deoliveira
Active Contributor
0 Kudos

Hi Vinay,

Try BAPI_ALM_NOTIF_DATA_MODIFY

Regards,

Custodio

0 Kudos

Hi,

The BAPI_NOTIF_DATA_MODIFY does not have Reference date(BEZDT) field.

Thanks

Vinay

raymond_giuseppi
Active Contributor
0 Kudos

Are you able to change this date via IW22 ?

Regards,

Raymond

0 Kudos

I found one standard FM for changing the reference date.

Thanks & Regards

Vinay