If I am submitted to 4-linked report program to background job. If 2 reports fails, what happen the result?
1. 3 and 4 report programs are executed or not
2. it give the 1 report program result or not
2007 Mar 23 7:54 AM
-job is stopped.
-following steps are not executed
-list of successful steps are available
A.
2007 Mar 23 7:54 AM
-job is stopped.
-following steps are not executed
-list of successful steps are available
A.
2007 Mar 23 8:01 AM
Hi,
System wil trigger on After Another, There is no link between One another,
So the 3 rd and 4 th will excute fine only.
2007 Mar 23 8:05 AM
hi Navin,
Check the following documentation
Detect if a report is submitted in backgorund
>In the start-of-slection event of a report, I would like to detect if the
>report
>is submitted as a background job.
>Is it possible ?
Yes, it is possible to determine at run-time wether a report is
submitted as a background job or not.
There is a system field for this purpose: SY-BATCH.
If this field is filled with 'X' the report was submitted in background,
if space the report was started in foreground.