PM Order header text need to be transfered to PR header text.

former_member217316
Contributor
0 Kudos

Hi All

We have a requirement where PM Order header text need to be transfered to PR header text.

I went through this [LINK|] but couldn't get any solution for the same.

Please let me know if this is feasible or not.

Thanks in advance.

Harsh

4 REPLIES 4

Former Member
0 Kudos

Hi

You can try to use BADI ME_PROCESS_PO_CUST

Extract header Text Using FM 'READ_TEXT'

Regards

Ajit

0 Kudos

Hi Ajit

Thanks for your reply.

We need the Work Order header text which can then be transferred to the PR Header text.

Regards,

Harsh

Former Member
0 Kudos

Hi,

You can use BADI "ME_REQ_POSTED".

In this BADI, you can read text from your PM order via FM 'READ_TEXT' and insert text into PR via FM 'SAVE_TEXT'.

When you call FM 'SAVE_TEXT', make sure input parameter "SAVEMODE_DIRECT" = ' '.

0 Kudos

Thanks for your response Ocean.

A sample code will be really helpful here. Basically I am looking into parameters to pass to READ_TEXT while deriving PM Order header text.

Thanks in advance.

Harsh